Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
82
matching recommendationsSIC | 2037 | Frozen Fruits And Vegetables |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0780 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,517 | $2,000 | Implemented |
OR0773 # 02 Y:2023 | 02 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,051 | $797 | Implemented |
OR0773 # 01 Y:2023 | 01 | 2023 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $5,439 | $1,278 | Implemented |
OR0610 # 05 Y:2013 | 05 | 2013 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $64,511 | $85,275 | Implemented |
OR0609 # 07 Y:2013 | 07 | 2013 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $117,782 | $160,770 | Implemented |
OR0565 # 06 Y:2011 | 06 | 2011 | HEAT WATER WITH EXHAUST HEAT | $77,370 | $96,750 | Implemented |
OR0565 # 03 Y:2011 | 03 | 2011 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $10,300 | $17,700 | Implemented |
OR0565 # 05 Y:2011 | 05 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,900 | $10,900 | Implemented |
OR0565 # 02 Y:2011 | 02 | 2011 | INSULATE BARE EQUIPMENT | $6,110 | $21,715 | Implemented |
OR0565 # 01 Y:2011 | 01 | 2011 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $14,900 | $9,340 | Implemented |
OR0561 # 03 Y:2010 | 03 | 2010 | UPGRADE CONTROLS ON COMPRESSORS | $14,426 | $7,234 | Implemented |
OR0561 # 06 Y:2010 | 06 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,786 | $10,046 | Implemented |
OR0561 # 07 Y:2010 | 07 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,321 | $3,321 | Implemented |
OR0561 # 02 Y:2010 | 02 | 2010 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $84,544 | $24,245 | Implemented |
OR0561 # 01 Y:2010 | 01 | 2010 | ISOLATE HOT OR COLD EQUIPMENT | $7,124 | $1,529 | Implemented |
OR0561 # 04 Y:2010 | 04 | 2010 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $18,820 | $19,635 | Implemented |
OR0561 # 05 Y:2010 | 05 | 2010 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $90,831 | $106,316 | Implemented |
OR0558 # 04 Y:2010 | 04 | 2010 | INSTALL OCCUPANCY SENSORS | $14,738 | $120,911 | Implemented |
OR0558 # 03 Y:2010 | 03 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,319 | $4,935 | Implemented |
OR0558 # 01 Y:2010 | 01 | 2010 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $6,602 | $2,965 | Implemented |
OR0558 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,102 | $7,102 | Implemented |
OR0459 # 05 Y:2004 | 05 | 2004 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $5,330 | $2,825 | Implemented |
OR0459 # 04 Y:2004 | 04 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $34,250 | $2,000 | Implemented |
OR0459 # 06 Y:2004 | 06 | 2004 | OPTIMIZE PLANT POWER FACTOR | $2,730 | $5,130 | Implemented |
OR0459 # 02 Y:2004 | 02 | 2004 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $9,750 | $300 | Implemented |