Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
169
matching recommendationsSIC | 26 | Paper And Allied Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD1025 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,051 | $340 | Implemented |
UD0950 # 10 Y:2016 | 10 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $240 | $460 | Implemented |
UD0950 # 13 Y:2016 | 13 | 2016 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $7,880 | $0 | Implemented |
UD0950 # 11 Y:2016 | 11 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $335 | $1,000 | Implemented |
UD0894 # 03 Y:2013 | 03 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,290 | $0 | Implemented |
UD0894 # 07 Y:2013 | 07 | 2013 | INSULATE BARE EQUIPMENT | $142 | $350 | Implemented |
UD0894 # 02 Y:2013 | 02 | 2013 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,885 | $0 | Implemented |
WV0464 # 06 Y:2013 | 06 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,550 | $32 | Implemented |
WV0464 # 07 Y:2013 | 07 | 2013 | DEVELOP A REPAIR/REPLACE POLICY | $1,256 | $1,068 | Implemented |
WV0464 # 05 Y:2013 | 05 | 2013 | INSTALL OCCUPANCY SENSORS | $4,654 | $984 | Implemented |
WV0464 # 11 Y:2013 | 11 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $323 | $500 | Implemented |
WV0464 # 04 Y:2013 | 04 | 2013 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,702 | $0 | Implemented |
WV0464 # 03 Y:2013 | 03 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,493 | $17,640 | Implemented |
UD0804 # 15 Y:2009 | 15 | 2009 | ISOLATE HOT OR COLD EQUIPMENT | $1,306 | $0 | Implemented |
UD0804 # 08 Y:2009 | 08 | 2009 | KEEP BOILER TUBES CLEAN | $8,490 | $600 | Implemented |
UD0804 # 11 Y:2009 | 11 | 2009 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,128 | $0 | Implemented |
UD0804 # 03 Y:2009 | 03 | 2009 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $35,001 | $9,000 | Implemented |
UD0804 # 05 Y:2009 | 05 | 2009 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $17,277 | $500 | Implemented |
UD0804 # 04 Y:2009 | 04 | 2009 | REPAIR OR REPLACE STEAM TRAPS | $23,089 | $4,000 | Implemented |
UD0804 # 02 Y:2009 | 02 | 2009 | AVOID COOLING OF PROCESS STREAMS OR MATERIALS THAT MUST SUBSEQUENTLY BE HEATED | $38,869 | $12,000 | Implemented |
UD0787 # 01 Y:2008 | 01 | 2008 | REDUCE VENTILATION AIR | $47,843 | $62,700 | Implemented |
UD0787 # 09 Y:2008 | 09 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,351 | $1,000 | Implemented |
UD0787 # 10 Y:2008 | 10 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $388 | $1,000 | Implemented |
UD0787 # 04 Y:2008 | 04 | 2008 | INSTALL / REPAIR INSULATION ON STEAM LINES | $9,025 | $2,424 | Implemented |
UD0787 # 02 Y:2008 | 02 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,242 | $107,122 | Implemented |