Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
91
matching recommendationsSIC | 2653 | Corrugated And Solid Fiber Boxes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0498 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,814 | $500 | Implemented |
SD0498 # 01 Y:2015 | 01 | 2015 | REPAIR AND ELIMINATE STEAM LEAKS | $14,239 | $1,000 | Implemented |
SD0498 # 05 Y:2015 | 05 | 2015 | INCREASE AMOUNT OF CONDENSATE RETURNED | $3,194 | $8,000 | Implemented |
SF0463 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $366 | $0 | Implemented |
SF0463 # 11 Y:2015 | 11 | 2015 | INSULATE FEEDWATER TANK | $490 | $993 | Implemented |
SF0463 # 15 Y:2015 | 15 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $3,394 | $16,788 | Implemented |
SF0463 # 08 Y:2015 | 08 | 2015 | REPAIR OR REPLACE STEAM TRAPS | $7,199 | $7,920 | Implemented |
SF0463 # 05 Y:2015 | 05 | 2015 | INSULATE BARE EQUIPMENT | $3,340 | $721 | Implemented |
SF0463 # 09 Y:2015 | 09 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,990 | $2,660 | Implemented |
SF0463 # 03 Y:2015 | 03 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,452 | $0 | Implemented |
SF0463 # 02 Y:2015 | 02 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,820 | $110 | Implemented |
SF0463 # 06 Y:2015 | 06 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $28,979 | $14,516 | Implemented |
SD0496 # 01 Y:2015 | 01 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $43,186 | $113,400 | Implemented |
SD0496 # 02 Y:2015 | 02 | 2015 | INSTALL OCCUPANCY SENSORS | $10,851 | $12,449 | Implemented |
SD0496 # 06 Y:2015 | 06 | 2015 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $869 | $1,356 | Implemented |
SD0496 # 05 Y:2015 | 05 | 2015 | USE PHOTOCELL CONTROLS | $2,674 | $2,420 | Implemented |
SD0496 # 03 Y:2015 | 03 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $9,239 | $7,006 | Implemented |
SD0494 # 02 Y:2015 | 02 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $47,366 | $73,800 | Implemented |
SD0494 # 03 Y:2015 | 03 | 2015 | INSTALL TIMERS AND/OR THERMOSTATS | $11,773 | $3,400 | Implemented |
SD0494 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,501 | $800 | Implemented |
LM0094 # 03 Y:2005 | 03 | 2005 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $57,780 | $50,000 | Implemented |
LM0094 # 02 Y:2005 | 02 | 2005 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,502 | $983 | Implemented |
LM0094 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,130 | $500 | Implemented |
SD0356 # 01 Y:2005 | 01 | 2005 | UPGRADE CONTROLS ON COMPRESSORS | $5,391 | $11,000 | Implemented |
SD0356 # 02 Y:2005 | 02 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,992 | $14,000 | Implemented |