Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
334
matching recommendationsSIC | 2869 | Industrial Organic Chemicals, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0750 # 03 Y:2006 | 03 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $155,000 | $187,200 | Implemented |
UD0750 # 04 Y:2006 | 04 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $79,000 | $45,000 | Implemented |
UD0750 # 06 Y:2006 | 06 | 2006 | INCREASE AMOUNT OF CONDENSATE RETURNED | $44,000 | $25,000 | Implemented |
UD0750 # 09 Y:2006 | 09 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $24,000 | $13,000 | Implemented |
UF0389 # 01 Y:2006 | 01 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $101,986 | $13,656 | Implemented |
UD0745 # 01 Y:2006 | 01 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $18,706 | $0 | Implemented |
UD0745 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,807 | $34,035 | Implemented |
UD0745 # 07 Y:2006 | 07 | 2006 | USE OPTIMUM THICKNESS INSULATION | $8,710 | $4,000 | Implemented |
UD0745 # 10 Y:2006 | 10 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,746 | $8,200 | Implemented |
UD0745 # 11 Y:2006 | 11 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,408 | $0 | Implemented |
UD0745 # 12 Y:2006 | 12 | 2006 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $941 | $0 | Implemented |
LE0226 # 01 Y:2006 | 01 | 2006 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $154,145 | $75,000 | Implemented |
LE0226 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $81,919 | $51,275 | Implemented |
LE0226 # 05 Y:2006 | 05 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $50,061 | $47,500 | Implemented |
LE0226 # 06 Y:2006 | 06 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $14,515 | $800 | Implemented |
LE0226 # 08 Y:2006 | 08 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,760 | $500 | Implemented |
UM0254 # 02 Y:2004 | 02 | 2004 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $9,650 | $2,200 | Implemented |
UM0254 # 06 Y:2004 | 06 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,010 | $1,080 | Implemented |
UM0254 # 03 Y:2004 | 03 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $6,907 | $0 | Implemented |
UM0254 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,479 | $1,038 | Implemented |
WI0459 # 04 Y:2004 | 04 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $340 | $640 | Implemented |
IC0060 # 01 Y:2003 | 01 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $148,006 | $13,000 | Implemented |
IC0060 # 02 Y:2003 | 02 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $8,832 | $13,240 | Implemented |
IC0060 # 03 Y:2003 | 03 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,390 | $20,640 | Implemented |
IC0060 # 04 Y:2003 | 04 | 2003 | USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) | $163,590 | $170,491 | Implemented |