Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
154
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0653 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,630 | $800 | Implemented |
UD0844 # 10 Y:2011 | 10 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $267 | $0 | Implemented |
UD0844 # 11 Y:2011 | 11 | 2011 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $13,123 | $1,000 | Implemented |
UD0844 # 14 Y:2011 | 14 | 2011 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $18,762 | $0 | Implemented |
UD0844 # 05 Y:2011 | 05 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,557 | $0 | Implemented |
MA0683 # 03 Y:2011 | 03 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,273 | $200 | Implemented |
MA0683 # 05 Y:2011 | 05 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $821 | $200 | Implemented |
MA0683 # 04 Y:2011 | 04 | 2011 | VENTILATION SYSTEM TO SHUT OFF WHEN ROOM IS NOT IN USE | $1,113 | $200 | Implemented |
MA0683 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $12,021 | $2,800 | Implemented |
MA0683 # 06 Y:2011 | 06 | 2011 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $486 | $100 | Implemented |
MA0682 # 04 Y:2011 | 04 | 2011 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $10,708 | $29,760 | Implemented |
MA0682 # 03 Y:2011 | 03 | 2011 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $11,594 | $0 | Implemented |
MA0682 # 05 Y:2011 | 05 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,468 | $7,325 | Implemented |
MA0681 # 03 Y:2011 | 03 | 2011 | INSTALL OCCUPANCY SENSORS | $1,163 | $1,265 | Implemented |
MA0681 # 01 Y:2011 | 01 | 2011 | REDUCE VENTILATION AIR | $6,162 | $9,261 | Implemented |
CO0650 # 01 Y:2011 | 01 | 2011 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,700 | $1,000 | Implemented |
CO0650 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,390 | $190 | Implemented |
CO0650 # 05 Y:2011 | 05 | 2011 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $740 | $1,470 | Implemented |
CO0650 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,420 | $9,240 | Implemented |
TT0082 # 04 Y:2011 | 04 | 2011 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,256 | $1,480 | Implemented |
TT0082 # 07 Y:2011 | 07 | 2011 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $952 | $2,625 | Implemented |
TT0082 # 05 Y:2011 | 05 | 2011 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,673 | $15 | Implemented |
TT0082 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,923 | $18,044 | Implemented |
DL0074 # 07 Y:2011 | 07 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,320 | $1,900 | Implemented |
DL0074 # 10 Y:2011 | 10 | 2011 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $510 | $1,300 | Implemented |