Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,948
matching recommendationsSIC | 3089 | Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0306 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,924 | $537 | Implemented |
IA0306 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,147 | $2,412 | Implemented |
IA0306 # 04 Y:2002 | 04 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,726 | $0 | Implemented |
IA0306 # 05 Y:2002 | 05 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,150 | $0 | Implemented |
UD0659 # 01 Y:2002 | 01 | 2002 | DEVELOP STANDARD OPERATING PROCEDURES | $103,190 | $31,120 | Implemented |
UD0659 # 05 Y:2002 | 05 | 2002 | OPTIMIZE PLANT POWER FACTOR | $5,400 | $6,750 | Implemented |
UD0659 # 08 Y:2002 | 08 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,464 | $1,000 | Implemented |
UD0659 # 10 Y:2002 | 10 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,776 | $120 | Implemented |
UD0659 # 15 Y:2002 | 15 | 2002 | DISCONNECT BALLASTS | $392 | $35 | Implemented |
IC0043 # 01 Y:2002 | 01 | 2002 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $700 | $578 | Implemented |
IC0043 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $21,789 | $81,125 | Implemented |
IC0043 # 03 Y:2002 | 03 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $117 | $1,822 | Implemented |
IC0043 # 05 Y:2002 | 05 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $965 | $1,169 | Implemented |
IC0043 # 06 Y:2002 | 06 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,481 | $3,120 | Implemented |
IC0043 # 07 Y:2002 | 07 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,358 | $26,100 | Implemented |
UD0657 # 01 Y:2002 | 01 | 2002 | DEVELOP STANDARD OPERATING PROCEDURES | $1,600,000 | $339,333 | Implemented |
UD0657 # 04 Y:2002 | 04 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,470 | $0 | Implemented |
MA0523 # 02 Y:2002 | 02 | 2002 | OPTIMIZE PLANT POWER FACTOR | $6,907 | $11,770 | Implemented |
MA0523 # 03 Y:2002 | 03 | 2002 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,108 | $0 | Implemented |
MA0523 # 04 Y:2002 | 04 | 2002 | PAY BILLS ON TIME TO AVOID LATE FEES | $1,510 | $0 | Implemented |
MA0523 # 06 Y:2002 | 06 | 2002 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $467 | $250 | Implemented |
MA0523 # 07 Y:2002 | 07 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $359 | $230 | Implemented |
AM0421 # 01 Y:2002 | 01 | 2002 | INSTALL EQUIPMENT TO MOVE PRODUCT | $9,360 | $7,880 | Implemented |
AM0421 # 02 Y:2002 | 02 | 2002 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $7,040 | $0 | Implemented |
AM0421 # 03 Y:2002 | 03 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,230 | $500 | Implemented |