Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
383
matching recommendationsSIC | 3231 | Products Of Purchased Glass |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0239 # 03 Y:1999 | 03 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $25,982 | $0 | Implemented |
UF0239 # 04 Y:1999 | 04 | 1999 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $53,580 | $0 | Implemented |
SF0175 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,293 | $3,150 | Implemented |
SF0175 # 04 Y:1999 | 04 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,740 | $1,817 | Implemented |
SF0175 # 07 Y:1999 | 07 | 1999 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,413 | $0 | Implemented |
SF0175 # 08 Y:1999 | 08 | 1999 | INSTALL SENSORS TO DETECT DEFECTS | $821,093 | $48,500 | Implemented |
SF0175 # 09 Y:1999 | 09 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $131,976 | $10,000 | Implemented |
SF0175 # 10 Y:1999 | 10 | 1999 | IMPROVE SPACE COMFORT CONDITIONING | $574,512 | $43,227 | Implemented |
UM0147 # 05 Y:1999 | 05 | 1999 | RECOVER AND REUSE WASTE MATERIAL | $1,436 | $0 | Implemented |
WV0177 # 09 Y:1999 | 09 | 1999 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $6,500 | $0 | Implemented |
WV0177 # 07 Y:1999 | 07 | 1999 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $1,300 | $40 | Implemented |
WV0177 # 06 Y:1999 | 06 | 1999 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $1,120 | $300 | Implemented |
WV0177 # 05 Y:1999 | 05 | 1999 | INSTALL SPECTRAL REFLECTORS / DELAMP | $3,419 | $4,965 | Implemented |
WV0177 # 04 Y:1999 | 04 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $697 | $0 | Implemented |
WV0177 # 03 Y:1999 | 03 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $270 | $450 | Implemented |
WV0177 # 01 Y:1999 | 01 | 1999 | USE SYNTHETIC LUBRICANT | $302 | $400 | Implemented |
WV0166 # 12 Y:1999 | 12 | 1999 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $3,840 | $1,260 | Implemented |
WV0166 # 14 Y:1999 | 14 | 1999 | RECOVER AND REUSE WASTE MATERIAL | $6,940 | $1,800 | Implemented |
WV0166 # 15 Y:1999 | 15 | 1999 | EXPAND OPERATIONS INTO UNUSED SPACE | $6,000 | $1,050 | Implemented |
WV0166 # 10 Y:1999 | 10 | 1999 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $7,120 | $1,260 | Implemented |
WV0166 # 08 Y:1999 | 08 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $54,120 | $0 | Implemented |
WV0166 # 06 Y:1999 | 06 | 1999 | TURN OFF EQUIPMENT WHEN NOT IN USE | $36 | $0 | Implemented |
WV0166 # 05 Y:1999 | 05 | 1999 | DISCONNECT BALLASTS | $203 | $80 | Implemented |
WV0166 # 04 Y:1999 | 04 | 1999 | INSULATE BARE EQUIPMENT | $24,192 | $5,439 | Implemented |
OK0559 # 04 Y:1998 | 04 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $318 | $660 | Implemented |