Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,274
matching recommendationsSIC | 34 | Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0118 # 08 Y:1998 | 08 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $774 | $350 | Implemented |
BD0118 # 10 Y:1998 | 10 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $501 | $0 | Implemented |
BD0118 # 11 Y:1998 | 11 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $448 | $450 | Implemented |
BD0118 # 12 Y:1998 | 12 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $374 | $360 | Implemented |
ME0245 # 01 Y:1998 | 01 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,696 | $0 | Implemented |
ME0245 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,163 | $5,970 | Implemented |
ME0245 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,398 | $400 | Implemented |
ME0245 # 04 Y:1998 | 04 | 1998 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,127 | $3,000 | Implemented |
ME0245 # 05 Y:1998 | 05 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,051 | $2,000 | Implemented |
ME0245 # 06 Y:1998 | 06 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $895 | $700 | Implemented |
ME0245 # 07 Y:1998 | 07 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $803 | $900 | Implemented |
ME0245 # 10 Y:1998 | 10 | 1998 | INSTALL / REPAIR INSULATION ON STEAM LINES | $443 | $174 | Implemented |
AM0328 # 03 Y:1998 | 03 | 1998 | OPTIMIZE PLANT POWER FACTOR | $11,750 | $0 | Implemented |
AM0328 # 07 Y:1998 | 07 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $500 | $500 | Implemented |
OR0319 # 01 Y:1998 | 01 | 1998 | ELIMINATE SHIFT | $200,000 | $2,500 | Implemented |
OR0319 # 02 Y:1998 | 02 | 1998 | SCHEDULE DELIVERIES ACCORDING TO DEMAND | $32,660 | $300,000 | Implemented |
OR0319 # 03 Y:1998 | 03 | 1998 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $31,569 | $931 | Implemented |
OR0319 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $833 | $1,000 | Implemented |
OR0319 # 05 Y:1998 | 05 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $355 | $1,750 | Implemented |
IA0194 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,107 | $21,359 | Implemented |
IA0194 # 03 Y:1998 | 03 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,197 | $4,877 | Implemented |
SD0201 # 01 Y:1998 | 01 | 1998 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,033 | $1,033 | Implemented |
SD0201 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,892 | $6,734 | Implemented |
SD0201 # 03 Y:1998 | 03 | 1998 | INSTALL TIMERS AND/OR THERMOSTATS | $1,393 | $300 | Implemented |
SD0201 # 04 Y:1998 | 04 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $13,056 | $0 | Implemented |