Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
47
matching recommendationsSIC | 349 | Misc. Fabricated Metal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1041 # 05 Y:2021 | 05 | 2021 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $614 | $219 | Implemented |
OK1041 # 03 Y:2021 | 03 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $896 | $1,927 | Implemented |
OK1041 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,223 | $1,690 | Implemented |
OK1041 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,337 | $28,697 | Implemented |
MZ0287 # 01 Y:2020 | 01 | 2020 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,540 | $2,484 | Implemented |
MZ0287 # 07 Y:2020 | 07 | 2020 | OPTIMIZE PLANT POWER FACTOR | $937 | $4,000 | Implemented |
MZ0287 # 06 Y:2020 | 06 | 2020 | INSTALL OCCUPANCY SENSORS | $2,755 | $5,978 | Implemented |
MZ0287 # 05 Y:2020 | 05 | 2020 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,939 | $356 | Implemented |
MZ0287 # 04 Y:2020 | 04 | 2020 | USE RADIANT HEATER FOR SPOT HEATING | $4,983 | $6,696 | Implemented |
MZ0287 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,049 | $14,550 | Implemented |
MZ0287 # 02 Y:2020 | 02 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,461 | $1,310 | Implemented |
OK0845 # 01 Y:2013 | 01 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,354 | $12,299 | Implemented |
OK0845 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,941 | $550 | Implemented |
OK0845 # 06 Y:2013 | 06 | 2013 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $318 | $1,584 | Implemented |
MZ0052 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,361 | $18,360 | Implemented |
MZ0052 # 04 Y:2010 | 04 | 2010 | OPTIMIZE PLANT POWER FACTOR | $9,103 | $8,984 | Implemented |
MZ0052 # 02 Y:2010 | 02 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,855 | $16,700 | Implemented |
KU0532 # 02 Y:1999 | 02 | 1999 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $8,040 | $20,000 | Implemented |
KU0532 # 08 Y:1999 | 08 | 1999 | RECYCLE CLEANING SOLVENT AND REUSE | $2,620 | $800 | Implemented |
KU0532 # 05 Y:1999 | 05 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $260 | $360 | Implemented |
KU0532 # 04 Y:1999 | 04 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $700 | $450 | Implemented |
KU0532 # 03 Y:1999 | 03 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $7,060 | $12,170 | Implemented |
KU0498 # 05 Y:1998 | 05 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $340 | $630 | Implemented |
KU0498 # 06 Y:1998 | 06 | 1998 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $320 | $0 | Implemented |
KU0498 # 08 Y:1998 | 08 | 1998 | IMPLEMENT A MACHINE AND COOLANT SUMP CLEANING PROGRAM TO MINIMIZE COOLANT CONTAMINATION | $3,150 | $1,450 | Implemented |