Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,093
matching recommendationsSIC | 35 | Industrial Machinery And Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0352 # 09 Y:2004 | 09 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $867,815 | $171 | Implemented |
IA0350 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $703 | $290 | Implemented |
IA0350 # 02 Y:2004 | 02 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $197 | $25 | Implemented |
IA0350 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $647 | $985 | Implemented |
IA0350 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $967 | $4,398 | Implemented |
IA0350 # 05 Y:2004 | 05 | 2004 | INSTALL OCCUPANCY SENSORS | $207 | $732 | Implemented |
IA0348 # 01 Y:2004 | 01 | 2004 | OPTIMIZE PLANT POWER FACTOR | $9,818 | $10,704 | Implemented |
IA0348 # 03 Y:2004 | 03 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $651 | $146 | Implemented |
IA0348 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,888 | $535 | Implemented |
IA0348 # 05 Y:2004 | 05 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,829 | $14,216 | Implemented |
IA0348 # 08 Y:2004 | 08 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,653 | $4,596 | Implemented |
OR0470 # 05 Y:2004 | 05 | 2004 | ELIMINATE/REDUCE AN OPERATION | $1,185 | $165 | Implemented |
BD0270 # 01 Y:2004 | 01 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,872 | $0 | Implemented |
BD0270 # 02 Y:2004 | 02 | 2004 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $13,615 | $24,000 | Implemented |
BD0270 # 07 Y:2004 | 07 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,382 | $750 | Implemented |
BD0270 # 08 Y:2004 | 08 | 2004 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,173 | $75 | Implemented |
BD0270 # 09 Y:2004 | 09 | 2004 | USE PHOTOCELL CONTROLS | $1,040 | $320 | Implemented |
BD0270 # 10 Y:2004 | 10 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $353 | $168 | Implemented |
CO0553 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,980 | $180 | Implemented |
MS0260 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $811 | $348 | Implemented |
MS0260 # 06 Y:2004 | 06 | 2004 | DISCONNECT BALLASTS | $341 | $408 | Implemented |
IA0347 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,623 | $920 | Implemented |
IA0347 # 03 Y:2004 | 03 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,243 | $1,090 | Implemented |
IA0347 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,608 | $2,591 | Implemented |
IA0347 # 05 Y:2004 | 05 | 2004 | INSTALL OCCUPANCY SENSORS | $1,911 | $1,820 | Implemented |