Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
61
matching recommendationsSIC | 3567 | Industrial Furnaces And Ovens |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0220 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $920 | $1,200 | Implemented |
UU0220 # 02 Y:2023 | 02 | 2023 | OPTIMIZE PLANT POWER FACTOR | $3,986 | $13,500 | Implemented |
UU0220 # 01 Y:2023 | 01 | 2023 | USE HEAT PUMP FOR SPACE CONDITIONING | $67,069 | $0 | Implemented |
UU0220 # 05 Y:2023 | 05 | 2023 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $1,160 | $50 | Implemented |
WI0467 # 03 Y:2004 | 03 | 2004 | INSTALL TIMERS AND/OR THERMOSTATS | $2,729 | $400 | Implemented |
WI0467 # 06 Y:2004 | 06 | 2004 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $345 | $640 | Implemented |
WI0467 # 04 Y:2004 | 04 | 2004 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $2,231 | $300 | Implemented |
WI0467 # 01 Y:2004 | 01 | 2004 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $15,905 | $15,000 | Implemented |
WI0428 # 03 Y:2002 | 03 | 2002 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,612 | $1,200 | Implemented |
WI0428 # 08 Y:2002 | 08 | 2002 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $804 | $2,000 | Implemented |
WI0427 # 02 Y:2002 | 02 | 2002 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,439 | $400 | Implemented |
WI0427 # 06 Y:2002 | 06 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $391 | $740 | Implemented |
BD0210 # 08 Y:2002 | 08 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $-124 | $281 | Implemented |
BD0210 # 02 Y:2002 | 02 | 2002 | ADD AREA LIGHTING SWITCHES | $3,792 | $2,700 | Implemented |
BD0210 # 03 Y:2002 | 03 | 2002 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $3,594 | $3,500 | Implemented |
BD0210 # 05 Y:2002 | 05 | 2002 | INSTALL OCCUPANCY SENSORS | $516 | $750 | Implemented |
BD0210 # 01 Y:2002 | 01 | 2002 | USE RADIANT HEATER FOR SPOT HEATING | $4,813 | $9,000 | Implemented |
BD0210 # 06 Y:2002 | 06 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $439 | $1,200 | Implemented |
BD0210 # 07 Y:2002 | 07 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $422 | $500 | Implemented |
BD0210 # 09 Y:2002 | 09 | 2002 | USE EVAPORATION TO CONCENTRATE MATERIAL | $406 | $1,200 | Implemented |
WV0127 # 04 Y:1997 | 04 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $391 | $200 | Implemented |
WV0127 # 03 Y:1997 | 03 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $243 | $480 | Implemented |
WV0127 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $718 | $807 | Implemented |
WV0127 # 02 Y:1997 | 02 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,628 | $4,080 | Implemented |
KU0476 # 11 Y:1997 | 11 | 1997 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $7,620 | $0 | Implemented |