Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,791
matching recommendationsSIC | 36 | Electronic & Other Electric Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0330 # 03 Y:2011 | 03 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $10,060 | $600 | Implemented |
NC0435 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $44,479 | $72,211 | Implemented |
NC0435 # 03 Y:2011 | 03 | 2011 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,887 | $7,760 | Implemented |
NC0435 # 04 Y:2011 | 04 | 2011 | INSTALL OCCUPANCY SENSORS | $661 | $1,911 | Implemented |
NC0435 # 06 Y:2011 | 06 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $295 | $1,500 | Implemented |
TT0072 # 01 Y:2011 | 01 | 2011 | USE OPTIMUM TEMPERATURE | $16,018 | $0 | Implemented |
TT0071 # 01 Y:2011 | 01 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $43,100 | $66,100 | Implemented |
TT0071 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,400 | $52,100 | Implemented |
TT0071 # 04 Y:2011 | 04 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,700 | $5 | Implemented |
NC0430 # 01 Y:2011 | 01 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,839 | $0 | Implemented |
NC0430 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,052 | $100 | Implemented |
NC0430 # 03 Y:2011 | 03 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,314 | $150 | Implemented |
NC0430 # 06 Y:2011 | 06 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,385 | $4,833 | Implemented |
SF0397 # 01 Y:2011 | 01 | 2011 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $12,161 | $0 | Implemented |
SF0397 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,394 | $0 | Implemented |
SF0397 # 05 Y:2011 | 05 | 2011 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,066 | $2,420 | Implemented |
SF0397 # 07 Y:2011 | 07 | 2011 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,428 | $6,271 | Implemented |
SF0397 # 08 Y:2011 | 08 | 2011 | INSTALL OCCUPANCY SENSORS | $3,294 | $7,163 | Implemented |
SF0397 # 09 Y:2011 | 09 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $19,656 | $79,881 | Implemented |
WV0425 # 04 Y:2011 | 04 | 2011 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $9,251 | $9,400 | Implemented |
WV0425 # 06 Y:2011 | 06 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,760 | $0 | Implemented |
WV0425 # 07 Y:2011 | 07 | 2011 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,578 | $3,004 | Implemented |
MA0668 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,378 | $1,800 | Implemented |
MA0668 # 02 Y:2011 | 02 | 2011 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $7,899 | $11,500 | Implemented |
MA0668 # 03 Y:2011 | 03 | 2011 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $3,401 | $11,610 | Implemented |