Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
367
matching recommendationsSIC | 3672 | Printed Circuit Boards |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0166 # 02 Y:2008 | 02 | 2008 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $70,996 | $1,200 | Implemented |
MI0166 # 03 Y:2008 | 03 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $30,899 | $41,800 | Implemented |
MI0166 # 04 Y:2008 | 04 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,060 | $1,210 | Implemented |
MI0166 # 05 Y:2008 | 05 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,713 | $40 | Implemented |
MA0613 # 05 Y:2007 | 05 | 2007 | INSULATE BARE EQUIPMENT | $507 | $256 | Implemented |
MA0613 # 03 Y:2007 | 03 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,574 | $53,250 | Implemented |
MA0613 # 02 Y:2007 | 02 | 2007 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $15,346 | $54,617 | Implemented |
MA0613 # 01 Y:2007 | 01 | 2007 | REDUCE VENTILATION AIR | $22,488 | $15,475 | Implemented |
CO0597 # 06 Y:2007 | 06 | 2007 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $630 | $850 | Implemented |
CO0597 # 02 Y:2007 | 02 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,820 | $140 | Implemented |
OK0733 # 07 Y:2006 | 07 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $442 | $1,360 | Implemented |
OK0733 # 06 Y:2006 | 06 | 2006 | INSTALL OCCUPANCY SENSORS | $1,460 | $3,919 | Implemented |
OK0733 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,077 | $9,738 | Implemented |
OK0733 # 03 Y:2006 | 03 | 2006 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $1,003 | $980 | Implemented |
OK0733 # 02 Y:2006 | 02 | 2006 | INSTALL OCCUPANCY SENSORS | $6,122 | $13,600 | Implemented |
AS0426 # 02 Y:2006 | 02 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $9,823 | $500 | Implemented |
AS0426 # 06 Y:2006 | 06 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,221 | $1,000 | Implemented |
AS0426 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $8,267 | $2,077 | Implemented |
AS0426 # 07 Y:2006 | 07 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,539 | $15,085 | Implemented |
CO0570 # 09 Y:2005 | 09 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $610 | $1,210 | Implemented |
CO0570 # 08 Y:2005 | 08 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,070 | $5,110 | Implemented |
CO0570 # 05 Y:2005 | 05 | 2005 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $680 | $340 | Implemented |
CO0570 # 02 Y:2005 | 02 | 2005 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $280 | $420 | Implemented |
CO0570 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,270 | $210 | Implemented |
CO0568 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,510 | $330 | Implemented |