Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,217
matching recommendationsSIC | 37 | Transportation Equipment |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0552 # 03 Y:1998 | 03 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $819 | $700 | Implemented |
OK0552 # 04 Y:1998 | 04 | 1998 | INSTALL OCCUPANCY SENSORS | $873 | $651 | Implemented |
OK0552 # 05 Y:1998 | 05 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $142 | $54 | Implemented |
OK0552 # 06 Y:1998 | 06 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $581 | $375 | Implemented |
OK0552 # 07 Y:1998 | 07 | 1998 | REDUCE EXCESSIVE BOILER BLOWDOWN | $1,324 | $5,000 | Implemented |
OK0552 # 08 Y:1998 | 08 | 1998 | INSULATE BARE EQUIPMENT | $193 | $209 | Implemented |
OK0553 # 01 Y:1998 | 01 | 1998 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $69,793 | $76,000 | Implemented |
OK0553 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,035 | $6,760 | Implemented |
OD0114 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,198 | $1,457 | Implemented |
OD0114 # 02 Y:1998 | 02 | 1998 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $143 | $80 | Implemented |
OD0114 # 03 Y:1998 | 03 | 1998 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $35 | $10 | Implemented |
OD0114 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,303 | $509 | Implemented |
AR0141 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,369 | $100 | Implemented |
AR0141 # 03 Y:1998 | 03 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $613 | $102 | Implemented |
BD0109 # 01 Y:1998 | 01 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,380 | $13,620 | Implemented |
BD0109 # 02 Y:1998 | 02 | 1998 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,513 | $3,513 | Implemented |
BD0109 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $733 | $375 | Implemented |
BD0109 # 05 Y:1998 | 05 | 1998 | USE SYNTHETIC LUBRICANT | $396 | $200 | Implemented |
BD0109 # 08 Y:1998 | 08 | 1998 | $263 | $0 | Implemented | |
TN0633 # 01 Y:1998 | 01 | 1998 | REUSE / RECYCLE/ SELL RUBBER PRODUCTS | $100,000 | $122,130 | Implemented |
TN0633 # 03 Y:1998 | 03 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,960 | $7,010 | Implemented |
TN0633 # 04 Y:1998 | 04 | 1998 | BURN A LESS EXPENSIVE GRADE OF FUEL | $2,770 | $5,450 | Implemented |
TN0633 # 05 Y:1998 | 05 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,625 | $7,110 | Implemented |
KU0492 # 02 Y:1998 | 02 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,750 | $700 | Implemented |
KU0492 # 05 Y:1998 | 05 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $400 | $1,000 | Implemented |