Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
122
matching recommendationsSIC | 3714 | Motor Vehicle Parts And Accessories |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0292 # 03 Y:2023 | 03 | 2023 | AIR CONDITION ONLY SPACE NECESSARY | $8,884 | $18,000 | Implemented |
TT0292 # 07 Y:2023 | 07 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,223 | $4,750 | Implemented |
TT0292 # 06 Y:2023 | 06 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,057 | $2,190 | Implemented |
TT0292 # 08 Y:2023 | 08 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,268 | $50 | Implemented |
TT0292 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,314 | $15,941 | Implemented |
TT0284 # 02 Y:2023 | 02 | 2023 | MINIMIZE WATER USAGE | $10,675 | $240 | Implemented |
TT0284 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,804 | $10,150 | Implemented |
TT0284 # 03 Y:2023 | 03 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,764 | $13,000 | Implemented |
TT0259 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $300,781 | $111,421 | Implemented |
TT0259 # 02 Y:2021 | 02 | 2021 | UPGRADE CONTROLS ON COMPRESSORS | $62,325 | $1,640 | Implemented |
TT0259 # 04 Y:2021 | 04 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,779 | $2,738 | Implemented |
TT0249 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $87,163 | $208,768 | Implemented |
TT0249 # 04 Y:2021 | 04 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,133 | $1,500 | Implemented |
TT0236 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,250 | $128,083 | Implemented |
TT0236 # 02 Y:2020 | 02 | 2020 | ADOPT IN-HOUSE MATERIAL GENERATION | $28,629 | $16,000 | Implemented |
TT0231 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $42,957 | $153,710 | Implemented |
TT0231 # 02 Y:2019 | 02 | 2019 | INSTALL COMMON HEADER ON COMPRESSORS | $13,982 | $1,050 | Implemented |
TT0231 # 06 Y:2019 | 06 | 2019 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $650 | $1,650 | Implemented |
TT0231 # 04 Y:2019 | 04 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,033 | $25 | Implemented |
TT0231 # 05 Y:2019 | 05 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $886 | $40 | Implemented |
TT0231 # 03 Y:2019 | 03 | 2019 | INSULATE BARE EQUIPMENT | $4,149 | $10,500 | Implemented |
TT0229 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,229 | $9,752 | Implemented |
TT0223 # 02 Y:2019 | 02 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $36,339 | $172,868 | Implemented |
TT0209 # 08 Y:2018 | 08 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,744 | $5,280 | Implemented |
TT0209 # 11 Y:2018 | 11 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $340 | $465 | Implemented |