Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
51
matching recommendationsSIC | 3714 | Motor Vehicle Parts And Accessories |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK1514 # 01 Y:2015 | 01 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $11,570 | $8,081 | Implemented |
UK1514 # 09 Y:2015 | 09 | 2015 | INSTALL OCCUPANCY SENSORS | $1,704 | $2,189 | Implemented |
UK1514 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,483 | $2,000 | Implemented |
UK1514 # 05 Y:2015 | 05 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $21,417 | $0 | Implemented |
UK1514 # 11 Y:2015 | 11 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,139 | $896 | Implemented |
UK1514 # 07 Y:2015 | 07 | 2015 | USE ONLY CERTIFIED MOTOR REPAIR SHOPS | $925 | $343 | Implemented |
UD0936 # 08 Y:2015 | 08 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,271 | $85,000 | Implemented |
UD0936 # 07 Y:2015 | 07 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $530 | $1,480 | Implemented |
UD0936 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,521 | $1,000 | Implemented |
UD0936 # 02 Y:2015 | 02 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $22,431 | $2,260 | Implemented |
UD0936 # 01 Y:2015 | 01 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,695 | $0 | Implemented |
UK1512 # 10 Y:2015 | 10 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,609 | $1,500 | Implemented |
UK1512 # 09 Y:2015 | 09 | 2015 | INSULATE FEEDWATER TANK | $1,278 | $994 | Implemented |
UK1512 # 06 Y:2015 | 06 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,652 | $1,750 | Implemented |
UK1512 # 04 Y:2015 | 04 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,209 | $3,940 | Implemented |
UK1512 # 01 Y:2015 | 01 | 2015 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $5,559 | $0 | Implemented |
UM0463 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $150,724 | $565,274 | Implemented |
UD0933 # 15 Y:2015 | 15 | 2015 | OPTIMIZE PLANT POWER FACTOR | $4,834 | $35,000 | Implemented |
UD0933 # 14 Y:2015 | 14 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,427 | $4,500 | Implemented |
UD0933 # 13 Y:2015 | 13 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $29,454 | $1,000 | Implemented |
UD0933 # 05 Y:2015 | 05 | 2015 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $4,075 | $0 | Implemented |
UD0933 # 03 Y:2015 | 03 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,840 | $0 | Implemented |
UD0932 # 10 Y:2015 | 10 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,373 | $0 | Implemented |
UD0932 # 06 Y:2015 | 06 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $7,232 | $933 | Implemented |
UD0932 # 01 Y:2015 | 01 | 2015 | ISOLATE HOT OR COLD EQUIPMENT | $99,668 | $17,675 | Implemented |