Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
789
matching recommendationsSIC | 4952 | Sewerage Systems |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0576 # 06 Y:2021 | 06 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $41,072 | $554,541 | Implemented |
OK1056 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $425 | $629 | Implemented |
OK1056 # 04 Y:2021 | 04 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $46 | $162 | Implemented |
SD0617 # 01 Y:2021 | 01 | 2021 | UPGRADE OBSOLETE EQUIPMENT | $387,076 | $608,562 | Implemented |
SD0617 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $101,052 | $3,024,848 | Implemented |
SD0617 # 03 Y:2021 | 03 | 2021 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $27,764 | $41,000 | Implemented |
UA0244 # 01 Y:2021 | 01 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,477 | $3,209 | Implemented |
UF0568 # 02 Y:2021 | 02 | 2021 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $20,147 | $49,165 | Implemented |
UF0568 # 03 Y:2021 | 03 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,182 | $12,247 | Implemented |
UF0568 # 05 Y:2021 | 05 | 2021 | INSTALL OCCUPANCY SENSORS | $3,117 | $9,240 | Implemented |
UF0568 # 09 Y:2021 | 09 | 2021 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $3,655 | $0 | Implemented |
UF0567 # 01 Y:2021 | 01 | 2021 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $123,727 | $246,613 | Implemented |
UF0567 # 02 Y:2021 | 02 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $95,985 | $228,343 | Implemented |
UF0567 # 03 Y:2021 | 03 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $42,803 | $42,764 | Implemented |
UF0567 # 04 Y:2021 | 04 | 2021 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $9,372 | $14,250 | Implemented |
UF0567 # 08 Y:2021 | 08 | 2021 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $5,867 | $0 | Implemented |
AM0828 # 01 Y:2021 | 01 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $26,110 | $1,050 | Implemented |
AM0828 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,720 | $4,470 | Implemented |
AM0828 # 04 Y:2021 | 04 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,950 | $8,890 | Implemented |
AM0828 # 05 Y:2021 | 05 | 2021 | INSTALL OCCUPANCY SENSORS | $1,530 | $1,360 | Implemented |
AM0828 # 06 Y:2021 | 06 | 2021 | USE SYNTHETIC LUBRICANT | $1,400 | $660 | Implemented |
NL0060 # 01 Y:2021 | 01 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,780 | $6,000 | Implemented |
NL0060 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,978 | $8,057 | Implemented |
NL0060 # 03 Y:2021 | 03 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $908 | $1,790 | Implemented |
AM0826 # 01 Y:2021 | 01 | 2021 | MINIMIZE WATER USAGE | $31,800 | $136,000 | Implemented |