Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,243
matching recommendationsARC | 2. | ENERGY MANAGEMENT |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0110 # 08 Y:2018 | 08 | 2018 | INSULATE BARE EQUIPMENT | $655 | $945 | Implemented |
IP0110 # 06 Y:2018 | 06 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,905 | $5,340 | Implemented |
IP0110 # 05 Y:2018 | 05 | 2018 | INSTALL OCCUPANCY SENSORS | $21,079 | $3,360 | Implemented |
IP0110 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,835 | $130 | Implemented |
IP0110 # 01 Y:2018 | 01 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $23,973 | $5 | Implemented |
TT0212 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $68,776 | $32,000 | Implemented |
TT0212 # 04 Y:2018 | 04 | 2018 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $38,635 | $13,000 | Implemented |
TT0212 # 09 Y:2018 | 09 | 2018 | INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS | $3,775 | $5,000 | Implemented |
TT0212 # 11 Y:2018 | 11 | 2018 | INSTALL OCCUPANCY SENSORS | $283 | $250 | Implemented |
AM0765 # 06 Y:2018 | 06 | 2018 | INSTALL OCCUPANCY SENSORS | $510 | $595 | Implemented |
AM0765 # 05 Y:2018 | 05 | 2018 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $2,740 | $0 | Implemented |
AM0765 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,060 | $1,000 | Implemented |
AM0765 # 02 Y:2018 | 02 | 2018 | OPTIMIZE PLANT POWER FACTOR | $71,530 | $81,610 | Implemented |
NL0026 # 02 Y:2018 | 02 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,570 | $69,390 | Implemented |
NL0026 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $450 | $1,000 | Implemented |
UF0522 # 09 Y:2018 | 09 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,753 | $688 | Implemented |
UF0522 # 08 Y:2018 | 08 | 2018 | INSTALL OCCUPANCY SENSORS | $4,644 | $797 | Implemented |
UF0522 # 07 Y:2018 | 07 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,481 | $1,413 | Implemented |
UF0522 # 06 Y:2018 | 06 | 2018 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,837 | $0 | Implemented |
UF0522 # 04 Y:2018 | 04 | 2018 | TURN OFF EQUIPMENT WHEN NOT IN USE | $10,267 | $0 | Implemented |
WV0567 # 09 Y:2018 | 09 | 2018 | DEVELOP A REPAIR/REPLACE POLICY | $408 | $563 | Implemented |
WV0567 # 08 Y:2018 | 08 | 2018 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $495 | $500 | Implemented |
WV0567 # 07 Y:2018 | 07 | 2018 | INSULATE BARE EQUIPMENT | $1,487 | $1,690 | Implemented |
WV0567 # 04 Y:2018 | 04 | 2018 | INSTALL OCCUPANCY SENSORS | $5,896 | $6,014 | Implemented |
NC0623 # 03 Y:2018 | 03 | 2018 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,320 | $1,203 | Implemented |