IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

20,407

matching recommendations
Reset
ARC 2.2 Thermal Systems
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
GT0389 # 02 Y:1989 02 1989 INSTALL / REPAIR INSULATION ON STEAM LINES $1,021 $895 Implemented
TN0380 # 02 Y:1989 02 1989 REPAIR AND ELIMINATE STEAM LEAKS $4,181 $75 Implemented
TN0384 # 01 Y:1989 01 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $11,074 $22,940 Implemented
TN0384 # 03 Y:1989 03 1989 REPAIR AND ELIMINATE STEAM LEAKS $3,266 $550 Implemented
TN0384 # 04 Y:1989 04 1989 INSTALL / REPAIR INSULATION ON STEAM LINES $2,833 $826 Implemented
TN0384 # 09 Y:1989 09 1989 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $87 $180 Implemented
TN0386 # 06 Y:1989 06 1989 USE OPTIMUM THICKNESS INSULATION $851 $735 Not Implemented
OR0067 # 01 Y:1989 01 1989 USE MINIMUM STEAM OPERATING PRESSURE $7,313 $0 Not Implemented
OR0067 # 04 Y:1989 04 1989 INCREASE AMOUNT OF CONDENSATE RETURNED $4,079 $4,000 Implemented
OR0067 # 07 Y:1989 07 1989 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $6,141 $14,400 Not Implemented
OR0068 # 07 Y:1989 07 1989 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $4,272 $2,814 Not Implemented
OK0297 # 01 Y:1989 01 1989 RECOVER WASTE HEAT FROM EQUIPMENT $2,160 $5,523 Not Implemented
OK0297 # 06 Y:1989 06 1989 INSTALL / REPAIR INSULATION ON STEAM LINES $1,017 $2,289 Implemented
OK0298 # 07 Y:1989 07 1989 RECOVER WASTE HEAT FROM EQUIPMENT $1,620 $980 Implemented
OK0300 # 03 Y:1989 03 1989 RECOVER WASTE HEAT FROM EQUIPMENT $640 $980 Not Implemented
RU0071 # 06 Y:1989 06 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $6,906 $6,800 Not Implemented
RU0073 # 07 Y:1989 07 1989 RECOVER WASTE HEAT FROM EQUIPMENT $3,530 $44,000 Not Implemented
MA0164 # 02 Y:1989 02 1989 INSULATE BARE EQUIPMENT $4,170 $3,456 Not Implemented
MA0164 # 03 Y:1989 03 1989 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $529 $500 Not Implemented
AM0074 # 07 Y:1989 07 1989 INSULATE BARE EQUIPMENT $665 $270 Implemented
CO0161 # 01 Y:1989 01 1989 AVOID FROST FORMATION ON EVAPORATORS $1,340 $3,000 Not Implemented
CO0161 # 03 Y:1989 03 1989 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $300 $100 Implemented
CO0161 # 07 Y:1989 07 1989 INSTALL / REPAIR INSULATION ON STEAM LINES $214 $350 Not Implemented
CO0161 # 08 Y:1989 08 1989 TURN OFF STEAM TRACING DURING MILD WEATHER $170 $200 Implemented
CO0163 # 01 Y:1989 01 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $720 $700 Not Implemented