Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,762
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0374 # 01 Y:2010 | 01 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $23,008 | $3,000 | Implemented |
BD0374 # 09 Y:2010 | 09 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $678 | $875 | Implemented |
BD0374 # 10 Y:2010 | 10 | 2010 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $440 | $1,000 | Implemented |
BD0371 # 02 Y:2010 | 02 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,099 | $59,000 | Implemented |
BD0371 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,855 | $4,900 | Implemented |
BD0371 # 04 Y:2010 | 04 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,181 | $10 | Implemented |
BD0371 # 06 Y:2010 | 06 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,199 | $8,511 | Implemented |
BD0372 # 06 Y:2010 | 06 | 2010 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,914 | $5,000 | Implemented |
BD0368 # 01 Y:2010 | 01 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,866 | $25,159 | Implemented |
BD0368 # 03 Y:2010 | 03 | 2010 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $329 | $410 | Implemented |
BD0368 # 06 Y:2010 | 06 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,857 | $0 | Implemented |
BD0366 # 01 Y:2010 | 01 | 2010 | INSTALL OCCUPANCY SENSORS | $9,620 | $210 | Implemented |
BD0366 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,837 | $2,700 | Implemented |
BD0366 # 05 Y:2010 | 05 | 2010 | IMPROVE LUBRICATION PRACTICES | $2,368 | $600 | Implemented |
BD0366 # 08 Y:2010 | 08 | 2010 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,581 | $6,400 | Implemented |
BD0362 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,931 | $36,000 | Implemented |
BD0362 # 02 Y:2009 | 02 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $398 | $325 | Implemented |
BD0362 # 03 Y:2009 | 03 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $701 | $100 | Implemented |
BD0362 # 04 Y:2009 | 04 | 2009 | USE SYNTHETIC LUBRICANT | $1,202 | $300 | Implemented |
BD0362 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,945 | $2,900 | Implemented |
BD0362 # 06 Y:2009 | 06 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,913 | $3,300 | Implemented |
BD0362 # 10 Y:2009 | 10 | 2009 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $2,248 | $520 | Implemented |
BD0360 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,208 | $20,180 | Implemented |
BD0360 # 03 Y:2009 | 03 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,222 | $1,000 | Implemented |
BD0360 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $25,740 | $2,700 | Implemented |