Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
46
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0722 # 01 Y:2001 | 01 | 2001 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $16,455 | $5,110 | Implemented |
GT0722 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $851 | $2,902 | Implemented |
GT0722 # 05 Y:2001 | 05 | 2001 | INSULATE FEEDWATER TANK | $153 | $220 | Implemented |
GT0724 # 05 Y:2001 | 05 | 2001 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $6,956 | $7,500 | Implemented |
GT0724 # 04 Y:2001 | 04 | 2001 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $4,279 | $5,900 | Implemented |
GT0724 # 03 Y:2001 | 03 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,832 | $1,800 | Implemented |
GT0723 # 04 Y:2001 | 04 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,036 | $350 | Implemented |
GT0723 # 03 Y:2001 | 03 | 2001 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,660 | $825 | Implemented |
GT0723 # 06 Y:2001 | 06 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,965 | $1,418 | Implemented |
GT0723 # 05 Y:2001 | 05 | 2001 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $76,655 | $0 | Implemented |
GT0723 # 01 Y:2001 | 01 | 2001 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $21,103 | $60,000 | Implemented |
GT0723 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,140 | $68,913 | Implemented |
GT0720 # 01 Y:2001 | 01 | 2001 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $337 | $1,000 | Implemented |
GT0720 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,472 | $6,151 | Implemented |
GT0720 # 02 Y:2001 | 02 | 2001 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $1,475 | $600 | Implemented |
GT0720 # 07 Y:2001 | 07 | 2001 | REDUCE EXCESSIVE BOILER BLOWDOWN | $1,320 | $50 | Implemented |
GT0720 # 05 Y:2001 | 05 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $277 | $324 | Implemented |
GT0717 # 07 Y:2001 | 07 | 2001 | FILTER AND REUSE HYDRAULIC OIL | $1,030 | $1,000 | Implemented |
GT0717 # 08 Y:2001 | 08 | 2001 | UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID | $6,000 | $25,180 | Implemented |
GT0717 # 09 Y:2001 | 09 | 2001 | $7,200 | $29,314 | Implemented | |
GT0717 # 01 Y:2001 | 01 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,765 | $16,300 | Implemented |
GT0717 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,700 | $10,500 | Implemented |
GT0717 # 06 Y:2001 | 06 | 2001 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,465 | $67,250 | Implemented |
GT0715 # 02 Y:2001 | 02 | 2001 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,380 | $0 | Implemented |
GT0715 # 04 Y:2001 | 04 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,725 | $28,875 | Implemented |