Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
84
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0093 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,546 | $700 | Implemented |
IC0093 # 01 Y:2004 | 01 | 2004 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,168 | $3,600 | Implemented |
IC0093 # 04 Y:2004 | 04 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $737 | $0 | Implemented |
IC0091 # 02 Y:2004 | 02 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,038 | $1,315 | Implemented |
IC0091 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,889 | $1,265 | Implemented |
IC0091 # 01 Y:2004 | 01 | 2004 | REPAIR OR REPLACE STEAM TRAPS | $1,701 | $638 | Implemented |
IC0090 # 02 Y:2004 | 02 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,918 | $300 | Implemented |
IC0090 # 04 Y:2004 | 04 | 2004 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,643 | $9,400 | Implemented |
IC0090 # 05 Y:2004 | 05 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $559 | $77 | Implemented |
IC0090 # 01 Y:2004 | 01 | 2004 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $17,317 | $0 | Implemented |
IC0088 # 03 Y:2004 | 03 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,563 | $459 | Implemented |
IC0088 # 06 Y:2004 | 06 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,547 | $400 | Implemented |
IC0088 # 01 Y:2004 | 01 | 2004 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,664 | $0 | Implemented |
IC0085 # 07 Y:2004 | 07 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $33,640 | $138,438 | Implemented |
IC0085 # 03 Y:2004 | 03 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,310 | $588 | Implemented |
IC0085 # 01 Y:2004 | 01 | 2004 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $25,215 | $2,944 | Implemented |
IC0085 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $36,746 | $18,000 | Implemented |
IC0085 # 02 Y:2004 | 02 | 2004 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,699 | $0 | Implemented |
IC0087 # 06 Y:2004 | 06 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $14,571 | $8,465 | Implemented |
IC0087 # 04 Y:2004 | 04 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $43,578 | $6,900 | Implemented |
IC0087 # 10 Y:2004 | 10 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,168 | $79,350 | Implemented |
IC0087 # 12 Y:2004 | 12 | 2004 | LOWER LIGHT FIXTURES IN HIGH CEILING AREAS | $592 | $174,800 | Implemented |
IC0087 # 07 Y:2004 | 07 | 2004 | INSULATE BARE EQUIPMENT | $28,383 | $56,925 | Implemented |
IC0087 # 03 Y:2004 | 03 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS | $216,557 | $4,311 | Implemented |
IC0082 # 03 Y:2004 | 03 | 2004 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $295,385 | $90,783 | Implemented |