Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
72
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0147 # 05 Y:1998 | 05 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $375 | $200 | Implemented |
NC0147 # 01 Y:1998 | 01 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,282 | $200 | Implemented |
NC0147 # 04 Y:1998 | 04 | 1998 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,356 | $4,000 | Implemented |
NC0147 # 02 Y:1998 | 02 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $610 | $500 | Implemented |
NC0147 # 06 Y:1998 | 06 | 1998 | $14,809 | $0 | Implemented | |
NC0152 # 05 Y:1998 | 05 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,160 | $0 | Implemented |
NC0152 # 07 Y:1998 | 07 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $563 | $200 | Implemented |
NC0152 # 03 Y:1998 | 03 | 1998 | COVER OPEN TANKS | $1,006 | $100 | Implemented |
NC0141 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $556 | $60 | Implemented |
NC0141 # 03 Y:1998 | 03 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,183 | $4,236 | Implemented |
NC0141 # 02 Y:1998 | 02 | 1998 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $5,943 | $10,000 | Implemented |
NC0141 # 07 Y:1998 | 07 | 1998 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $1,861 | $200 | Implemented |
NC0141 # 04 Y:1998 | 04 | 1998 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $31,048 | $4,000 | Implemented |
NC0145 # 06 Y:1998 | 06 | 1998 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $1,125 | $150 | Implemented |
NC0145 # 05 Y:1998 | 05 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $22,875 | $100 | Implemented |
NC0149 # 03 Y:1998 | 03 | 1998 | $6,400 | $1,000 | Implemented | |
NC0149 # 02 Y:1998 | 02 | 1998 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,438 | $100 | Implemented |
NC0149 # 06 Y:1998 | 06 | 1998 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $4,320 | $800 | Implemented |
NC0149 # 04 Y:1998 | 04 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $938 | $200 | Implemented |
NC0149 # 05 Y:1998 | 05 | 1998 | RECYCLE CLEANING SOLVENT AND REUSE | $1,472 | $100 | Implemented |
NC0150 # 05 Y:1998 | 05 | 1998 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $2,244 | $4,400 | Implemented |
NC0150 # 04 Y:1998 | 04 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $244 | $800 | Implemented |
NC0148 # 04 Y:1998 | 04 | 1998 | $63,429 | $80,000 | Implemented | |
NC0148 # 02 Y:1998 | 02 | 1998 | REDUCE FLUID FLOW RATES | $304 | $550 | Implemented |
NC0148 # 03 Y:1998 | 03 | 1998 | $7,677 | $10,000 | Implemented |