IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,631

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD0579 # 06 Y:1999 06 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $910 $0 Implemented
UD0578 # 01 Y:1999 01 1999 INSTALL SHELVES / RACKS TO UTILIZE UNUSED SPACE $323,997 $26,940 Implemented
UD0578 # 03 Y:1999 03 1999 INSTALL EQUIPMENT TO MOVE PRODUCT $19,500 $8,600 Implemented
UD0578 # 04 Y:1999 04 1999 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $17,671 $3,000 Implemented
UD0578 # 06 Y:1999 06 1999 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $5,242 $0 Implemented
UM0147 # 05 Y:1999 05 1999 RECOVER AND REUSE WASTE MATERIAL $1,436 $0 Implemented
UD0576 # 03 Y:1999 03 1999 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $10,377 $4,700 Implemented
UD0576 # 06 Y:1999 06 1999 USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER $1,407 $1,000 Implemented
UD0575 # 03 Y:1999 03 1999 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION $39,515 $10,000 Implemented
UD0575 # 04 Y:1999 04 1999 RECOVER WASTE HEAT FROM EQUIPMENT $14,341 $15,000 Implemented
UD0574 # 04 Y:1999 04 1999 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,572 $0 Implemented
UD0573 # 01 Y:1999 01 1999 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $238,622 $0 Implemented
UD0573 # 02 Y:1999 02 1999 RECYCLE CASTING SAND $159,120 $310,000 Implemented
UD0573 # 05 Y:1999 05 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $9,523 $14,669 Implemented
UD0572 # 02 Y:1999 02 1999 USE PLASTIC PALLETS INSTEAD OF WOOD $38,960 $110,457 Implemented
UD0572 # 04 Y:1999 04 1999 INSTALL SPECTRAL REFLECTORS / DELAMP $9,457 $-27,115 Implemented
UD0571 # 01 Y:1999 01 1999 RECYCLE CASTING SAND $227,844 $135,000 Implemented
UD0571 # 04 Y:1999 04 1999 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $21,000 $64,000 Implemented
UD0571 # 08 Y:1999 08 1999 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $5,582 $0 Implemented
UD0570 # 01 Y:1999 01 1999 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $27,963 $0 Implemented
UD0570 # 03 Y:1999 03 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $4,148 $200 Implemented
UD0569 # 02 Y:1999 02 1999 INCREASE USE OF AUTOMATION $65,250 $0 Implemented
UD0569 # 05 Y:1999 05 1999 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $6,848 $632 Implemented
UD0568 # 03 Y:1999 03 1999 CHANGE ZONE REHEAT COILS TO VARIABLE AIR VOLUME BOXES $5,171 $4,000 Implemented
UD0567 # 01 Y:1999 01 1999 INSTALL AUTOMATIC PACKING EQUIPMENT $1,501,920 $1,075,000 Implemented