Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,622
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0801 # 02 Y:2010 | 02 | 2010 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $4,599 | $34,948 | Implemented |
OK0801 # 03 Y:2010 | 03 | 2010 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $9,699 | $3,000 | Implemented |
OK0801 # 04 Y:2010 | 04 | 2010 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $995 | $2,625 | Implemented |
OK0801 # 12 Y:2010 | 12 | 2010 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $4,196 | $21,075 | Implemented |
OK0800 # 02 Y:2010 | 02 | 2010 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $4,667 | $2,700 | Implemented |
OK0800 # 03 Y:2010 | 03 | 2010 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $209 | $334 | Implemented |
OK0800 # 04 Y:2010 | 04 | 2010 | INSTALL OCCUPANCY SENSORS | $860 | $1,865 | Implemented |
OK0800 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,134 | $706 | Implemented |
OK0800 # 06 Y:2010 | 06 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,134 | $1,678 | Implemented |
OK0798 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,085 | $5,205 | Implemented |
OK0798 # 04 Y:2010 | 04 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $203 | $2,009 | Implemented |
OK0798 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $28,826 | $900 | Implemented |
OK0798 # 06 Y:2010 | 06 | 2010 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $16,240 | $0 | Implemented |
OK0798 # 07 Y:2010 | 07 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,000 | $0 | Implemented |
OK0798 # 08 Y:2010 | 08 | 2010 | INSULATE BARE EQUIPMENT | $8,199 | $2,430 | Implemented |
OK0798 # 11 Y:2010 | 11 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,120 | $1,991 | Implemented |
OK0796 # 02 Y:2010 | 02 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,028 | $14,578 | Implemented |
OK0796 # 03 Y:2010 | 03 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,129 | $5,526 | Implemented |
OK0796 # 05 Y:2010 | 05 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,383 | $500 | Implemented |
OK0796 # 08 Y:2010 | 08 | 2010 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $786 | $1,850 | Implemented |
OK0795 # 04 Y:2010 | 04 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,677 | $1,100 | Implemented |
OK0795 # 07 Y:2010 | 07 | 2010 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $896 | $5,000 | Implemented |
OK0795 # 08 Y:2010 | 08 | 2010 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,751 | $1,680 | Implemented |
OK0792 # 01 Y:2010 | 01 | 2010 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,543 | $3,114 | Implemented |
OK0792 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $959 | $750 | Implemented |