IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,539

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WV0479 # 06 Y:2013 06 2013 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $7,444 $1,100 Implemented
WV0479 # 07 Y:2013 07 2013 INSTALL OCCUPANCY SENSORS $6,892 $1,275 Implemented
WV0479 # 11 Y:2013 11 2013 REPAIR OR REPLACE STEAM TRAPS $4,104 $6,095 Implemented
WV0479 # 12 Y:2013 12 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,996 $595 Implemented
WV0479 # 13 Y:2013 13 2013 INSTALL / REPAIR INSULATION ON STEAM LINES $2,332 $3,845 Implemented
WV0479 # 14 Y:2013 14 2013 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $559 $50 Implemented
LE0369 # 01 Y:2013 01 2013 INSTALL OCCUPANCY SENSORS $8,050 $19,339 Implemented
LE0369 # 02 Y:2013 02 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,100 $14,365 Implemented
LE0369 # 04 Y:2013 04 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,258 $7,350 Implemented
LE0369 # 05 Y:2013 05 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $50,065 $1,470 Implemented
LE0369 # 06 Y:2013 06 2013 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $50,836 $87,600 Implemented
LE0369 # 07 Y:2013 07 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,083 $1,000 Implemented
LE0369 # 08 Y:2013 08 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $18,023 $32,025 Implemented
LE0355 # 04 Y:2013 04 2013 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,970 $2,640 Implemented
LE0355 # 07 Y:2013 07 2013 INSTALL TIMERS AND/OR THERMOSTATS $1,174 $1,200 Implemented
LE0355 # 09 Y:2013 09 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,879 $1,000 Implemented
DL0108 # 01 Y:2013 01 2013 TURN OFF EQUIPMENT WHEN NOT IN USE $39,709 $0 Implemented
DL0108 # 03 Y:2013 03 2013 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $13,367 $0 Implemented
DL0108 # 04 Y:2013 04 2013 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,687 $270 Implemented
DL0108 # 05 Y:2013 05 2013 INSTALL TIMERS AND/OR THERMOSTATS $500 $200 Implemented
DL0108 # 07 Y:2013 07 2013 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE $543 $0 Implemented
WV0473 # 04 Y:2013 04 2013 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM $3,703 $1,000 Implemented
WV0473 # 05 Y:2013 05 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,539 $7,466 Implemented
WV0473 # 06 Y:2013 06 2013 INSULATE BARE EQUIPMENT $2,574 $3,281 Implemented
WV0473 # 09 Y:2013 09 2013 DEVELOP A REPAIR/REPLACE POLICY $497 $566 Implemented