IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

158,413

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0042 # 06 Y:1988 06 1988 USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS $36,759 $0 Not Implemented
OR0043 # 01 Y:1988 01 1988 USE MINIMUM STEAM OPERATING PRESSURE $506 $0 Implemented
OR0043 # 02 Y:1988 02 1988 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $471 $258 Not Implemented
OR0043 # 03 Y:1988 03 1988 INSULATE BARE EQUIPMENT $1,171 $627 Implemented
OR0043 # 04 Y:1988 04 1988 INSTALL / REPAIR INSULATION ON STEAM LINES $1,477 $1,900 Implemented
OR0043 # 05 Y:1988 05 1988 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $433 $908 Implemented
OR0043 # 06 Y:1988 06 1988 OPTIMIZE PLANT POWER FACTOR $2,458 $5,400 Implemented
OR0043 # 07 Y:1988 07 1988 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $5,196 $12,635 Not Implemented
OR0044 # 01 Y:1988 01 1988 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $11,498 $0 Implemented
OR0044 # 02 Y:1988 02 1988 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,775 $500 Implemented
OR0044 # 03 Y:1988 03 1988 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT $3,200 $1,108 Implemented
OR0044 # 04 Y:1988 04 1988 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $1,512 $676 Implemented
OR0044 # 05 Y:1988 05 1988 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $3,162 $2,550 Not Implemented
OR0044 # 06 Y:1988 06 1988 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $297 $250 Implemented
OR0044 # 07 Y:1988 07 1988 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $10,545 $0 Not Implemented
OR0044 # 08 Y:1988 08 1988 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,958 $1,911 Implemented
OR0044 # 09 Y:1988 09 1988 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $280 $275 Not Implemented
OR0044 # 10 Y:1988 10 1988 OPTIMIZE PLANT POWER FACTOR $14,889 $19,500 Not Implemented
OR0044 # 11 Y:1988 11 1988 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $1,525 $3,063 Implemented
OR0045 # 01 Y:1988 01 1988 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $1,601 $320 Not Implemented
OR0045 # 02 Y:1988 02 1988 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $614 $513 Not Implemented
OR0045 # 03 Y:1988 03 1988 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $61 $64 Not Implemented
OR0045 # 04 Y:1988 04 1988 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $3,612 $5,792 Not Implemented
OR0045 # 05 Y:1988 05 1988 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,758 $8,921 Implemented
OR0045 # 06 Y:1988 06 1988 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $1,542 $3,258 Not Implemented