Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
619
matching recommendationsNAICS | 3115 | Dairy Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0407 # 06 Y:2012 | 06 | 2012 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,437 | $1,299 | Implemented |
SF0404 # 02 Y:2011 | 02 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,243 | $0 | Implemented |
SF0404 # 03 Y:2011 | 03 | 2011 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $257 | $22 | Implemented |
SF0404 # 04 Y:2011 | 04 | 2011 | INSTALL / REPAIR INSULATION ON STEAM LINES | $17,934 | $5,426 | Implemented |
SF0404 # 08 Y:2011 | 08 | 2011 | INSTALL OCCUPANCY SENSORS | $697 | $1,356 | Implemented |
SF0404 # 10 Y:2011 | 10 | 2011 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $676 | $1,569 | Implemented |
LL0356 # 01 Y:2011 | 01 | 2011 | INCREASE AMOUNT OF CONDENSATE RETURNED | $35,965 | $89,664 | Implemented |
LL0356 # 02 Y:2011 | 02 | 2011 | INSULATE BARE EQUIPMENT | $9,420 | $840 | Implemented |
LL0356 # 05 Y:2011 | 05 | 2011 | INSULATE BARE EQUIPMENT | $6,412 | $1,127 | Implemented |
LL0356 # 08 Y:2011 | 08 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,666 | $360 | Implemented |
LL0356 # 13 Y:2011 | 13 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $80 | $66 | Implemented |
BD0393 # 03 Y:2011 | 03 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,288 | $107,000 | Implemented |
BD0393 # 06 Y:2011 | 06 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $201 | $10 | Implemented |
BD0393 # 07 Y:2011 | 07 | 2011 | INSTALL OCCUPANCY SENSORS | $155 | $300 | Implemented |
UF0443 # 01 Y:2011 | 01 | 2011 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,607 | $0 | Implemented |
UF0443 # 02 Y:2011 | 02 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $38,731 | $42,492 | Implemented |
UF0443 # 05 Y:2011 | 05 | 2011 | INSTALL TIMERS AND/OR THERMOSTATS | $562 | $75 | Implemented |
UF0443 # 06 Y:2011 | 06 | 2011 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $19,349 | $2,235 | Implemented |
SF0393 # 01 Y:2011 | 01 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,408 | $720 | Implemented |
SF0393 # 02 Y:2011 | 02 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $99,396 | $33,822 | Implemented |
SF0393 # 03 Y:2011 | 03 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,385 | $4,330 | Implemented |
SF0393 # 07 Y:2011 | 07 | 2011 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $32,171 | $34,310 | Implemented |
SF0393 # 08 Y:2011 | 08 | 2011 | INSULATE BARE EQUIPMENT | $6,132 | $17,178 | Implemented |
SF0393 # 09 Y:2011 | 09 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,350 | $25,921 | Implemented |
SF0393 # 10 Y:2011 | 10 | 2011 | INSTALL OCCUPANCY SENSORS | $3,016 | $14,478 | Implemented |