Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
179
matching recommendationsNAICS | 3132 | Fabric Mills |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0566 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $788 | $200 | Implemented |
NC0566 # 06 Y:2016 | 06 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,988 | $100 | Implemented |
NC0566 # 03 Y:2016 | 03 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,757 | $5,000 | Implemented |
NC0566 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $54,183 | $44,349 | Implemented |
NC0566 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $231,779 | $419,073 | Implemented |
UA0157 # 05 Y:2016 | 05 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $430 | $1,520 | Implemented |
MA0755 # 03 Y:2016 | 03 | 2016 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $10,196 | $21,560 | Implemented |
MA0742 # 08 Y:2015 | 08 | 2015 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $4,024 | $11,650 | Implemented |
MA0742 # 06 Y:2015 | 06 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,465 | $11,685 | Implemented |
MA0742 # 05 Y:2015 | 05 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $8,116 | $9,000 | Implemented |
MA0742 # 03 Y:2015 | 03 | 2015 | INSTALL / REPAIR INSULATION ON STEAM LINES | $24,583 | $5,560 | Implemented |
MA0742 # 02 Y:2015 | 02 | 2015 | OPTIMIZE PLANT POWER FACTOR | $38,357 | $25,972 | Implemented |
NC0513 # 01 Y:2014 | 01 | 2014 | DEVELOP A REPAIR/REPLACE POLICY | $137,290 | $454,945 | Implemented |
NC0513 # 16 Y:2014 | 16 | 2014 | INSULATE FEEDWATER TANK | $438 | $257 | Implemented |
NC0513 # 13 Y:2014 | 13 | 2014 | REPAIR AND ELIMINATE STEAM LEAKS | $20,840 | $20,000 | Implemented |
NC0513 # 12 Y:2014 | 12 | 2014 | REPAIR OR REPLACE STEAM TRAPS | $40,007 | $6,200 | Implemented |
NC0513 # 11 Y:2014 | 11 | 2014 | KEEP BOILER TUBES CLEAN | $48,265 | $15,000 | Implemented |
NC0513 # 09 Y:2014 | 09 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $835 | $240 | Implemented |
NC0513 # 08 Y:2014 | 08 | 2014 | INSTALL OCCUPANCY SENSORS | $3,462 | $3,470 | Implemented |
NC0513 # 05 Y:2014 | 05 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $325 | $175 | Implemented |
NC0513 # 04 Y:2014 | 04 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,428 | $100 | Implemented |
NC0513 # 03 Y:2014 | 03 | 2014 | UPGRADE CONTROLS ON COMPRESSORS | $21,458 | $10,000 | Implemented |
NC0513 # 02 Y:2014 | 02 | 2014 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $89,082 | $860 | Implemented |
NC0510 # 05 Y:2014 | 05 | 2014 | REPAIR OR REPLACE STEAM TRAPS | $26,718 | $67,500 | Implemented |
NC0510 # 08 Y:2014 | 08 | 2014 | INSTALL OCCUPANCY SENSORS | $1,444 | $2,082 | Implemented |