Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,389
matching recommendationsNAICS | 325 | Chemical Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0516 # 06 Y:2006 | 06 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $430 | $0 | Implemented |
UD0750 # 02 Y:2006 | 02 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $226,890 | $120,000 | Implemented |
UD0750 # 03 Y:2006 | 03 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $155,000 | $187,200 | Implemented |
UD0750 # 04 Y:2006 | 04 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $79,000 | $45,000 | Implemented |
UD0750 # 06 Y:2006 | 06 | 2006 | INCREASE AMOUNT OF CONDENSATE RETURNED | $44,000 | $25,000 | Implemented |
UD0750 # 09 Y:2006 | 09 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $24,000 | $13,000 | Implemented |
UF0389 # 01 Y:2006 | 01 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $101,986 | $13,656 | Implemented |
AS0430 # 02 Y:2006 | 02 | 2006 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $9,545 | $7,500 | Implemented |
AS0430 # 03 Y:2006 | 03 | 2006 | INSULATE BARE EQUIPMENT | $3 | $1,077 | Implemented |
AS0430 # 04 Y:2006 | 04 | 2006 | INSTALL SKYLIGHTS | $782 | $4,400 | Implemented |
UD0745 # 01 Y:2006 | 01 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $18,706 | $0 | Implemented |
UD0745 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,807 | $34,035 | Implemented |
UD0745 # 07 Y:2006 | 07 | 2006 | USE OPTIMUM THICKNESS INSULATION | $8,710 | $4,000 | Implemented |
UD0745 # 10 Y:2006 | 10 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,746 | $8,200 | Implemented |
UD0745 # 11 Y:2006 | 11 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,408 | $0 | Implemented |
UD0745 # 12 Y:2006 | 12 | 2006 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $941 | $0 | Implemented |
UM0306 # 01 Y:2006 | 01 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,385 | $2,500 | Implemented |
UM0306 # 04 Y:2006 | 04 | 2006 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $8,336 | $7,520 | Implemented |
UM0306 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,571 | $9,421 | Implemented |
UM0306 # 07 Y:2006 | 07 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,558 | $197 | Implemented |
WV0346 # 01 Y:2006 | 01 | 2006 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $12,230 | $1,143 | Implemented |
WV0346 # 02 Y:2006 | 02 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,998 | $13,688 | Implemented |
WV0346 # 06 Y:2006 | 06 | 2006 | INSULATE BARE EQUIPMENT | $1,502 | $737 | Implemented |
WV0346 # 07 Y:2006 | 07 | 2006 | DEVELOP A REPAIR/REPLACE POLICY | $850 | $230 | Implemented |