Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
186
matching recommendationsNAICS | 326121 | Unlaminated Plastics Profile Shape Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0196 # 06 Y:2021 | 06 | 2021 | INSULATE BARE EQUIPMENT | $1,842 | $2,864 | Implemented |
AM0791 # 02 Y:2019 | 02 | 2019 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $56,640 | $5,000 | Implemented |
AM0791 # 03 Y:2019 | 03 | 2019 | OPTIMIZE PLANT POWER FACTOR | $40,100 | $66,545 | Implemented |
AM0791 # 06 Y:2019 | 06 | 2019 | PAY UTILITY BILLS ON TIME | $540 | $0 | Implemented |
AM0791 # 01 Y:2019 | 01 | 2019 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $282,870 | $5,000 | Implemented |
AM0791 # 07 Y:2019 | 07 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $335 | $8 | Implemented |
AM0781 # 05 Y:2019 | 05 | 2019 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $445 | $780 | Implemented |
AM0781 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,710 | $7,720 | Implemented |
UD0981 # 08 Y:2018 | 08 | 2018 | INSULATE BARE EQUIPMENT | $6,131 | $4,525 | Implemented |
UD0981 # 01 Y:2018 | 01 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,044 | $0 | Implemented |
UD0981 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,028 | $500 | Implemented |
OK0976 # 07 Y:2017 | 07 | 2017 | INSTALL SET-BACK TIMERS | $1,177 | $240 | Implemented |
OK0976 # 08 Y:2017 | 08 | 2017 | KEEP EQUIPMENT CLEAN | $885 | $240 | Implemented |
OK0976 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,176 | $61,707 | Implemented |
OK0976 # 02 Y:2017 | 02 | 2017 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $8,586 | $3,840 | Implemented |
OK0976 # 01 Y:2017 | 01 | 2017 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $31,812 | $180,000 | Implemented |
OK0964 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,682 | $38,281 | Implemented |
LE0419 # 03 Y:2016 | 03 | 2016 | INSTALL TIMERS AND/OR THERMOSTATS | $2,202 | $1,830 | Implemented |
LE0419 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $43,060 | $25,900 | Implemented |
LE0419 # 04 Y:2016 | 04 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $66,277 | $63,000 | Implemented |
LE0419 # 07 Y:2016 | 07 | 2016 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $41,911 | $70,000 | Implemented |
LE0419 # 06 Y:2016 | 06 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $38,176 | $61,332 | Implemented |
LE0419 # 01 Y:2016 | 01 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,334 | $1,000 | Implemented |
OK0934 # 04 Y:2016 | 04 | 2016 | INSULATE BARE EQUIPMENT | $63,243 | $3,161 | Implemented |
OK0934 # 03 Y:2016 | 03 | 2016 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $134,039 | $1,300 | Implemented |