Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
179
matching recommendationsNAICS | 326121 | Unlaminated Plastics Profile Shape Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0781 # 03 Y:2019 | 03 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,710 | $7,720 | Implemented |
UD0981 # 08 Y:2018 | 08 | 2018 | INSULATE BARE EQUIPMENT | $6,131 | $4,525 | Implemented |
UD0981 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,028 | $500 | Implemented |
UD0981 # 01 Y:2018 | 01 | 2018 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,044 | $0 | Implemented |
OK0976 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,176 | $61,707 | Implemented |
OK0976 # 07 Y:2017 | 07 | 2017 | INSTALL SET-BACK TIMERS | $1,177 | $240 | Implemented |
OK0976 # 02 Y:2017 | 02 | 2017 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $8,586 | $3,840 | Implemented |
OK0976 # 01 Y:2017 | 01 | 2017 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $31,812 | $180,000 | Implemented |
OK0976 # 08 Y:2017 | 08 | 2017 | KEEP EQUIPMENT CLEAN | $885 | $240 | Implemented |
OK0964 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,682 | $38,281 | Implemented |
LE0419 # 03 Y:2016 | 03 | 2016 | INSTALL TIMERS AND/OR THERMOSTATS | $2,202 | $1,830 | Implemented |
LE0419 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $43,060 | $25,900 | Implemented |
LE0419 # 04 Y:2016 | 04 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $66,277 | $63,000 | Implemented |
LE0419 # 07 Y:2016 | 07 | 2016 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $41,911 | $70,000 | Implemented |
LE0419 # 06 Y:2016 | 06 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $38,176 | $61,332 | Implemented |
LE0419 # 01 Y:2016 | 01 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,334 | $1,000 | Implemented |
OK0934 # 04 Y:2016 | 04 | 2016 | INSULATE BARE EQUIPMENT | $63,243 | $3,161 | Implemented |
OK0934 # 03 Y:2016 | 03 | 2016 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $134,039 | $1,300 | Implemented |
SU0389 # 06 Y:2015 | 06 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,731 | $2,974 | Implemented |
SU0389 # 10 Y:2015 | 10 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $257 | $1,070 | Implemented |
SU0389 # 08 Y:2015 | 08 | 2015 | INSTALL / REPAIR INSULATION ON STEAM LINES | $119 | $123 | Implemented |
SU0389 # 09 Y:2015 | 09 | 2015 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $372 | $804 | Implemented |
SU0389 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,064 | $2,148 | Implemented |
SU0389 # 04 Y:2015 | 04 | 2015 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $10,554 | $3,085 | Implemented |
SU0389 # 03 Y:2015 | 03 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $516 | $0 | Implemented |