Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
63
matching recommendationsNAICS | 332410 | Power Boiler and Heat Exchanger Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LS2316 # 06 Y:2023 | 06 | 2023 | INSTALL OCCUPANCY SENSORS | $460 | $753 | Implemented |
LS2316 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $33,726 | $4,515 | Implemented |
LS2316 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,894 | $135 | Implemented |
OK1062 # 01 Y:2022 | 01 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,294 | $2,732 | Implemented |
OK1062 # 02 Y:2022 | 02 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,554 | $0 | Implemented |
OK1062 # 04 Y:2022 | 04 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $101 | $580 | Implemented |
OK1062 # 05 Y:2022 | 05 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,957 | $30,186 | Implemented |
NL0033 # 01 Y:2019 | 01 | 2019 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $39,609 | $71,240 | Implemented |
NL0033 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $919 | $1,000 | Implemented |
MZ0262 # 01 Y:2019 | 01 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,670 | $37,061 | Implemented |
MZ0262 # 02 Y:2019 | 02 | 2019 | INSTALL OCCUPANCY SENSORS | $3,589 | $1,350 | Implemented |
NC0594 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $979 | $100 | Implemented |
NC0594 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $41,372 | $77,272 | Implemented |
NC0594 # 03 Y:2017 | 03 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $5,016 | $8,200 | Implemented |
NC0594 # 02 Y:2017 | 02 | 2017 | INSTALL OCCUPANCY SENSORS | $5,666 | $2,982 | Implemented |
NC0594 # 06 Y:2017 | 06 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,732 | $50 | Implemented |
NC0594 # 04 Y:2017 | 04 | 2017 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,502 | $1,000 | Implemented |
SU0383 # 07 Y:2015 | 07 | 2015 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $218 | $471 | Implemented |
SU0383 # 08 Y:2015 | 08 | 2015 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $104 | $256 | Implemented |
SU0383 # 01 Y:2015 | 01 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $288 | $0 | Implemented |
SU0383 # 03 Y:2015 | 03 | 2015 | ELIMINATE/REDUCE AN OPERATION | $11,567 | $5,737 | Implemented |
OK0860 # 06 Y:2013 | 06 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,722 | $1,750 | Implemented |
OK0860 # 12 Y:2013 | 12 | 2013 | INSTALL OCCUPANCY SENSORS | $445 | $3,675 | Implemented |
AM0586 # 05 Y:2010 | 05 | 2010 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $13,725 | $0 | Implemented |
AM0586 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $30,790 | $3,000 | Implemented |