Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,801
matching recommendationsNAICS | 336 | Transportation Equipment Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0266 # 02 Y:2014 | 02 | 2014 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $8,400 | $800 | Implemented |
MI0266 # 03 Y:2014 | 03 | 2014 | USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES | $7,871 | $640 | Implemented |
MI0266 # 05 Y:2014 | 05 | 2014 | INSTALL SKYLIGHTS | $5,746 | $630 | Implemented |
MI0266 # 06 Y:2014 | 06 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,486 | $1,310 | Implemented |
MI0266 # 07 Y:2014 | 07 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,344 | $9,120 | Implemented |
MI0266 # 08 Y:2014 | 08 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,899 | $80 | Implemented |
MI0266 # 09 Y:2014 | 09 | 2014 | USE PHOTOCELL CONTROLS | $1,450 | $360 | Implemented |
AM0663 # 01 Y:2014 | 01 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,960 | $24,700 | Implemented |
AM0663 # 03 Y:2014 | 03 | 2014 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $5,730 | $0 | Implemented |
AM0663 # 04 Y:2014 | 04 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,790 | $55 | Implemented |
OK0894 # 04 Y:2014 | 04 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $853 | $551 | Implemented |
OK0894 # 05 Y:2014 | 05 | 2014 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $543 | $1,111 | Implemented |
OK0894 # 06 Y:2014 | 06 | 2014 | INSTALL TIMERS AND/OR THERMOSTATS | $9,056 | $2,750 | Implemented |
OK0894 # 07 Y:2014 | 07 | 2014 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $9,286 | $6,400 | Implemented |
OK0894 # 08 Y:2014 | 08 | 2014 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,062 | $1,409 | Implemented |
OK0894 # 11 Y:2014 | 11 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,260 | $2,090 | Implemented |
TT0139 # 02 Y:2014 | 02 | 2014 | DISCONNECT BALLASTS | $280 | $100 | Implemented |
TT0139 # 03 Y:2014 | 03 | 2014 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $13,460 | $500 | Implemented |
UA0126 # 05 Y:2014 | 05 | 2014 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $3,304 | $583 | Implemented |
UA0126 # 06 Y:2014 | 06 | 2014 | INSTALL TIMERS AND/OR THERMOSTATS | $4,317 | $625 | Implemented |
UD0907 # 01 Y:2014 | 01 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,297 | $28,275 | Implemented |
UD0907 # 04 Y:2014 | 04 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $762 | $1,000 | Implemented |
UD0907 # 05 Y:2014 | 05 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $518 | $0 | Implemented |
UD0907 # 06 Y:2014 | 06 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $314 | $500 | Implemented |
UD0907 # 08 Y:2014 | 08 | 2014 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $4,440 | $0 | Implemented |