Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
198
matching recommendationsSIC | 203 | Preserved Fruits And Vegetables |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0780 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,517 | $2,000 | Implemented |
OR0773 # 01 Y:2023 | 01 | 2023 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $5,439 | $1,278 | Implemented |
OR0773 # 02 Y:2023 | 02 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,051 | $797 | Implemented |
OR0704 # 02 Y:2018 | 02 | 2018 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $127,144 | $201,450 | Implemented |
OR0610 # 05 Y:2013 | 05 | 2013 | MODERATE COOLING TOWER OUTLET TEMPERATURE | $64,511 | $85,275 | Implemented |
OR0609 # 07 Y:2013 | 07 | 2013 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $117,782 | $160,770 | Implemented |
OR0565 # 03 Y:2011 | 03 | 2011 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $10,300 | $17,700 | Implemented |
OR0565 # 02 Y:2011 | 02 | 2011 | INSULATE BARE EQUIPMENT | $6,110 | $21,715 | Implemented |
OR0565 # 05 Y:2011 | 05 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,900 | $10,900 | Implemented |
OR0565 # 01 Y:2011 | 01 | 2011 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $14,900 | $9,340 | Implemented |
OR0565 # 06 Y:2011 | 06 | 2011 | HEAT WATER WITH EXHAUST HEAT | $77,370 | $96,750 | Implemented |
OR0561 # 03 Y:2010 | 03 | 2010 | UPGRADE CONTROLS ON COMPRESSORS | $14,426 | $7,234 | Implemented |
OR0561 # 06 Y:2010 | 06 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,786 | $10,046 | Implemented |
OR0561 # 05 Y:2010 | 05 | 2010 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $90,831 | $106,316 | Implemented |
OR0561 # 01 Y:2010 | 01 | 2010 | ISOLATE HOT OR COLD EQUIPMENT | $7,124 | $1,529 | Implemented |
OR0561 # 02 Y:2010 | 02 | 2010 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $84,544 | $24,245 | Implemented |
OR0561 # 07 Y:2010 | 07 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,321 | $3,321 | Implemented |
OR0561 # 04 Y:2010 | 04 | 2010 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $18,820 | $19,635 | Implemented |
OR0558 # 02 Y:2010 | 02 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,102 | $7,102 | Implemented |
OR0558 # 03 Y:2010 | 03 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,319 | $4,935 | Implemented |
OR0558 # 04 Y:2010 | 04 | 2010 | INSTALL OCCUPANCY SENSORS | $14,738 | $120,911 | Implemented |
OR0558 # 01 Y:2010 | 01 | 2010 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $6,602 | $2,965 | Implemented |
OR0556 # 05 Y:2010 | 05 | 2010 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $3,131 | $2,861 | Implemented |
OR0556 # 01 Y:2010 | 01 | 2010 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $542 | $0 | Implemented |
OR0556 # 06 Y:2010 | 06 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,320 | $2,320 | Implemented |