Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
220
matching recommendationsSIC | 226 | Textile Finishing, Except Wool |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0754 # 11 Y:2003 | 11 | 2003 | RECOVER AND REUSE COOLING WATER | $293,681 | $201,600 | Implemented |
GT0743 # 01 Y:2002 | 01 | 2002 | USE MINIMUM STEAM OPERATING PRESSURE | $1,259 | $0 | Implemented |
GT0743 # 04 Y:2002 | 04 | 2002 | USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER | $10,781 | $1,720 | Implemented |
MA0516 # 07 Y:2002 | 07 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $966 | $625 | Implemented |
MA0516 # 06 Y:2002 | 06 | 2002 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,589 | $5,200 | Implemented |
MA0516 # 01 Y:2002 | 01 | 2002 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $151,365 | $135,000 | Implemented |
MA0516 # 04 Y:2002 | 04 | 2002 | INSULATE BARE EQUIPMENT | $5,343 | $8,400 | Implemented |
MA0516 # 05 Y:2002 | 05 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,745 | $460 | Implemented |
NC0225 # 08 Y:2001 | 08 | 2001 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $28,105 | $100,000 | Implemented |
NC0225 # 07 Y:2001 | 07 | 2001 | REPAIR AND ELIMINATE STEAM LEAKS | $8,655 | $3,500 | Implemented |
NC0225 # 06 Y:2001 | 06 | 2001 | KEEP BOILER TUBES CLEAN | $3,649 | $13,000 | Implemented |
NC0225 # 04 Y:2001 | 04 | 2001 | ELIMINATE COMBUSTIBLE GAS IN FLUE GAS | $15,365 | $5,000 | Implemented |
NC0225 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,625 | $33,848 | Implemented |
NC0225 # 01 Y:2001 | 01 | 2001 | DEVELOP A REPAIR/REPLACE POLICY | $2,783 | $1,895 | Implemented |
LM0021 # 04 Y:2001 | 04 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $29,054 | $400 | Implemented |
LM0021 # 03 Y:2001 | 03 | 2001 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,649 | $6,000 | Implemented |
LM0021 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $40,680 | $48,707 | Implemented |
LM0021 # 01 Y:2001 | 01 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,082 | $857 | Implemented |
GT0708 # 07 Y:2001 | 07 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,650 | $21,400 | Implemented |
GT0708 # 01 Y:2001 | 01 | 2001 | MOVE BOILER TO MORE EFFICIENT LOCATION | $7,140 | $0 | Implemented |
GT0708 # 02 Y:2001 | 02 | 2001 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,765 | $0 | Implemented |
GT0708 # 04 Y:2001 | 04 | 2001 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $38,843 | $13,500 | Implemented |
GT0708 # 06 Y:2001 | 06 | 2001 | REPAIR OR REPLACE STEAM TRAPS | $9,164 | $10,500 | Implemented |
NC0204 # 07 Y:2000 | 07 | 2000 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $4,074 | $1,000 | Implemented |
NC0204 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,133 | $257 | Implemented |