Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
310
matching recommendationsSIC | 2499 | Wood Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0368 # 04 Y:2000 | 04 | 2000 | ADD ADDITIONAL PRODUCTION SHIFT | $5,000 | $0 | Implemented |
DS0170 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $589 | $224 | Implemented |
DS0170 # 05 Y:2000 | 05 | 2000 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $1,419 | $45 | Implemented |
MO0276 # 04 Y:2000 | 04 | 2000 | USE SYNTHETIC LUBRICANT | $161 | $160 | Implemented |
MO0276 # 02 Y:2000 | 02 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $544 | $263 | Implemented |
MO0276 # 05 Y:2000 | 05 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $460 | $0 | Implemented |
ME0285 # 05 Y:2000 | 05 | 2000 | INSTALL / REPAIR INSULATION ON STEAM LINES | $339 | $600 | Implemented |
ME0285 # 04 Y:2000 | 04 | 2000 | INSTALL / REPAIR INSULATION ON STEAM LINES | $706 | $1,772 | Implemented |
ME0285 # 02 Y:2000 | 02 | 2000 | USE ONLY AMOUNT OF PACKAGING MATERIAL NECESSARY | $3,500 | $0 | Implemented |
ME0285 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,698 | $16,582 | Implemented |
NC0167 # 01 Y:1999 | 01 | 1999 | ADJUST BURNERS FOR EFFICIENT OPERATION | $1,244 | $2,400 | Implemented |
NC0167 # 04 Y:1999 | 04 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,229 | $5,323 | Implemented |
NC0167 # 05 Y:1999 | 05 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $503 | $143 | Implemented |
NC0167 # 08 Y:1999 | 08 | 1999 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $25,000 | $1,000 | Implemented |
HO0191 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,167 | $5,870 | Implemented |
HO0191 # 02 Y:1999 | 02 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,826 | $120 | Implemented |
HO0191 # 04 Y:1999 | 04 | 1999 | REPLACE HIGH RESISTANCE DUCTS, PIPES, AND FITTINGS | $875 | $400 | Implemented |
HO0191 # 07 Y:1999 | 07 | 1999 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $1,125 | $500 | Implemented |
HO0191 # 08 Y:1999 | 08 | 1999 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $450 | $1,000 | Implemented |
OD0120 # 04 Y:1998 | 04 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $246,500 | $180,480 | Implemented |
OD0119 # 03 Y:1998 | 03 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $281 | $490 | Implemented |
OD0119 # 02 Y:1998 | 02 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,251 | $8,135 | Implemented |
OD0119 # 06 Y:1998 | 06 | 1998 | UPGRADE CONTROLS ON COMPRESSORS | $1,518 | $100 | Implemented |
OD0119 # 05 Y:1998 | 05 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,153 | $400 | Implemented |
OD0119 # 04 Y:1998 | 04 | 1998 | INSTALL OCCUPANCY SENSORS | $126 | $100 | Implemented |