Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
190
matching recommendationsSIC | 2951 | Asphalt Paving Mixtures And Blocks |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0545 # 01 Y:2019 | 01 | 2019 | INSULATE BARE EQUIPMENT | $1,151 | $1,194 | Implemented |
SF0545 # 06 Y:2019 | 06 | 2019 | USE SOLAR HEAT TO MAKE ELECTRICTY | $238,757 | $1,300,334 | Implemented |
OR0715 # 04 Y:2019 | 04 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $948 | $0 | Implemented |
OR0715 # 03 Y:2019 | 03 | 2019 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,204 | $0 | Implemented |
MA0785 # 01 Y:2017 | 01 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,893 | $20,000 | Implemented |
MA0785 # 03 Y:2017 | 03 | 2017 | KEEP BOILER TUBES CLEAN | $1,014 | $1,200 | Implemented |
OR0680 # 03 Y:2017 | 03 | 2017 | ADJUST BURNERS FOR EFFICIENT OPERATION | $2,467 | $1,000 | Implemented |
OR0680 # 01 Y:2017 | 01 | 2017 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $45,000 | $66,392 | Implemented |
OR0680 # 04 Y:2017 | 04 | 2017 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,732 | $3,529 | Implemented |
MI0249 # 06 Y:2013 | 06 | 2013 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $2,451 | $347 | Implemented |
MI0249 # 05 Y:2013 | 05 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,223 | $2,520 | Implemented |
MI0249 # 03 Y:2013 | 03 | 2013 | INCREASE EFFICIENCY OF TRUCKS | $14,224 | $11,600 | Implemented |
MI0249 # 01 Y:2013 | 01 | 2013 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $1,845,922 | $2,000,000 | Implemented |
MI0249 # 07 Y:2013 | 07 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,546 | $1,660 | Implemented |
MI0249 # 08 Y:2013 | 08 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,904 | $80 | Implemented |
MI0247 # 05 Y:2013 | 05 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,525 | $1,660 | Implemented |
MI0247 # 08 Y:2013 | 08 | 2013 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $870 | $347 | Implemented |
MI0247 # 06 Y:2013 | 06 | 2013 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,908 | $2,520 | Implemented |
MI0247 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,027 | $8,010 | Implemented |
SU0335 # 03 Y:2013 | 03 | 2013 | BURN A LESS EXPENSIVE GRADE OF FUEL | $288,725 | $218,600 | Implemented |
SU0335 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $866 | $2,820 | Implemented |
SU0335 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,709 | $5,124 | Implemented |
UM0416 # 02 Y:2012 | 02 | 2012 | INSTALL OCCUPANCY SENSORS | $222 | $450 | Implemented |
IA0390 # 07 Y:2006 | 07 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,305 | $896 | Implemented |
IA0390 # 01 Y:2006 | 01 | 2006 | ADJUST BURNERS FOR EFFICIENT OPERATION | $53,488 | $1,000 | Implemented |