IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

114

matching recommendations
Reset
SIC 34 Fabricated Metal Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UA0261 # 02 Y:2022 02 2022 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $21,987 $82,172 Implemented
UA0243 # 04 Y:2021 04 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,058 $9,682 Implemented
UA0243 # 03 Y:2021 03 2021 OPTIMIZE PLANT POWER FACTOR $45,219 $10,941 Implemented
UA0240 # 02 Y:2021 02 2021 OPTIMIZE PLANT POWER FACTOR $8,528 $60,000 Implemented
UA0240 # 03 Y:2021 03 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $18,894 $9,682 Implemented
UA0240 # 01 Y:2021 01 2021 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $10,059 $800 Implemented
UA0222 # 01 Y:2020 01 2020 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $32,232 $92,405 Implemented
UA0222 # 04 Y:2020 04 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $10,527 $7,775 Implemented
UA0217 # 06 Y:2019 06 2019 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $5,941 $50 Implemented
UA0217 # 03 Y:2019 03 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,910 $1,395 Implemented
UA0206 # 02 Y:2019 02 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,544 $1,372 Implemented
UA0206 # 05 Y:2019 05 2019 INSULATE BARE EQUIPMENT $7,065 $8,101 Implemented
UA0199 # 08 Y:2018 08 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $604 $919 Implemented
UA0199 # 06 Y:2018 06 2018 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $182 $698 Implemented
UA0199 # 01 Y:2018 01 2018 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $10,877 $13,552 Implemented
UA0199 # 02 Y:2018 02 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $6,483 $9,013 Implemented
UA0186 # 04 Y:2017 04 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,615 $4,645 Implemented
UA0186 # 02 Y:2017 02 2017 INSTALL OCCUPANCY SENSORS $1,872 $740 Implemented
UA0186 # 05 Y:2017 05 2017 INSTALL TIMERS AND/OR THERMOSTATS $1,297 $60 Implemented
UA0173 # 08 Y:2017 08 2017 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,811 $150 Implemented
UA0173 # 03 Y:2017 03 2017 INSTALL OCCUPANCY SENSORS $2,924 $880 Implemented
UA0173 # 02 Y:2017 02 2017 USE PHOTOCELL CONTROLS $5,531 $2,748 Implemented
UA0173 # 05 Y:2017 05 2017 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $15,474 $5,695 Implemented
UA0161 # 01 Y:2016 01 2016 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,411 $8,838 Implemented
UA0161 # 02 Y:2016 02 2016 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $632 $100 Implemented