Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
55
matching recommendationsSIC | 3483 | Ammunition, Exc. For Small Arms, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0421 # 07 Y:2011 | 07 | 2011 | DEVELOP A REPAIR/REPLACE POLICY | $4,203 | $841 | Implemented |
WV0421 # 08 Y:2011 | 08 | 2011 | INSULATE BARE EQUIPMENT | $4,166 | $1,910 | Implemented |
WV0421 # 16 Y:2011 | 16 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $266 | $191 | Implemented |
LL0324 # 01 Y:2009 | 01 | 2009 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $51,066 | $5,850 | Implemented |
OR0523 # 01 Y:2007 | 01 | 2007 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $35,000 | $60,000 | Implemented |
OR0523 # 04 Y:2007 | 04 | 2007 | INSULATE BARE EQUIPMENT | $1,220 | $1,160 | Implemented |
UF0309 # 02 Y:2002 | 02 | 2002 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,774 | $3,840 | Implemented |
UF0309 # 09 Y:2002 | 09 | 2002 | HIRE ADDITIONAL PERSONNEL TO REDUCE CHANGEOUT TIME | $8,100 | $2,160 | Implemented |
UF0309 # 03 Y:2002 | 03 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,173 | $23,719 | Implemented |
UF0309 # 01 Y:2002 | 01 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,113 | $340 | Implemented |
AS0288 # 05 Y:2000 | 05 | 2000 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $15,129 | $11,400 | Implemented |
AS0288 # 03 Y:2000 | 03 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,416 | $3,589 | Implemented |
AS0288 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $468 | $1,130 | Implemented |
AS0288 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,163 | $2,397 | Implemented |
AS0287 # 06 Y:2000 | 06 | 2000 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $25,067 | $24,000 | Implemented |
AS0287 # 03 Y:2000 | 03 | 2000 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $501 | $240 | Implemented |
AS0287 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,756 | $17,407 | Implemented |
SD0238 # 05 Y:2000 | 05 | 2000 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $25,314 | $100,000 | Implemented |
SD0238 # 03 Y:2000 | 03 | 2000 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $838 | $1,880 | Implemented |
SD0238 # 02 Y:2000 | 02 | 2000 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $13,294 | $11,825 | Implemented |
SD0238 # 01 Y:2000 | 01 | 2000 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $21,910 | $10,250 | Implemented |
WI0256 # 03 Y:1996 | 03 | 1996 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $3,375 | $0 | Implemented |
WI0256 # 04 Y:1996 | 04 | 1996 | MINIMIZE WATER USAGE | $1,975 | $0 | Implemented |
WI0256 # 10 Y:1996 | 10 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $335 | $0 | Implemented |
WI0256 # 11 Y:1996 | 11 | 1996 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $273 | $500 | Implemented |