Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
322
matching recommendationsSIC | 3559 | Special Industry Machinery, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DS0098 # 01 Y:1997 | 01 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,701 | $50 | Implemented |
DS0098 # 02 Y:1997 | 02 | 1997 | TURN OFF EQUIPMENT WHEN NOT IN USE | $13,974 | $9,200 | Implemented |
UM0084 # 03 Y:1997 | 03 | 1997 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $10,308 | $40,000 | Implemented |
UM0084 # 04 Y:1997 | 04 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $735 | $600 | Implemented |
UM0084 # 05 Y:1997 | 05 | 1997 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,333 | $1,400 | Implemented |
UM0084 # 07 Y:1997 | 07 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $279 | $0 | Implemented |
UM0084 # 08 Y:1997 | 08 | 1997 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $37,448 | $1,200 | Implemented |
UM0084 # 09 Y:1997 | 09 | 1997 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $9,060 | $6,710 | Implemented |
NV0076 # 01 Y:1997 | 01 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $134 | $37 | Implemented |
NV0076 # 02 Y:1997 | 02 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,161 | $300 | Implemented |
OR0282 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $212 | $664 | Implemented |
OR0282 # 02 Y:1996 | 02 | 1996 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $240 | $0 | Implemented |
OR0282 # 04 Y:1996 | 04 | 1996 | UPGRADE CONTROLS ON COMPRESSORS | $280 | $300 | Implemented |
OR0277 # 02 Y:1996 | 02 | 1996 | USE OTHER WASTE CONCENTRATION METHODS | $5,324 | $10,000 | Implemented |
OR0277 # 03 Y:1996 | 03 | 1996 | UPGRADE CONTROLS ON COMPRESSORS | $952 | $3,840 | Implemented |
OR0277 # 04 Y:1996 | 04 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $927 | $4,907 | Implemented |
WV0096 # 01 Y:1996 | 01 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,010 | $302 | Implemented |
WV0096 # 02 Y:1996 | 02 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $7,892 | $4,029 | Implemented |
WV0096 # 03 Y:1996 | 03 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $275 | $200 | Implemented |
WV0096 # 05 Y:1996 | 05 | 1996 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $3,406 | $490 | Implemented |
UD0485 # 01 Y:1996 | 01 | 1996 | OPTIMIZE PLANT POWER FACTOR | $600 | $0 | Implemented |
UD0485 # 03 Y:1996 | 03 | 1996 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $6,528 | $250 | Implemented |
UD0485 # 04 Y:1996 | 04 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,249 | $12,150 | Implemented |
UD0485 # 06 Y:1996 | 06 | 1996 | RECOVERY METALS FROM RINSE WATER(EVAP., ION EXCHANGE, RO, ELECTROLYSIS, ELECTRODIALYSIS) AND REUSE RINSE WATER | $18,918 | $6,000 | Implemented |
MS0053 # 01 Y:1996 | 01 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $4,882 | $3,720 | Implemented |