IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

412

matching recommendations
Reset
ARC 2.2 Thermal Systems
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
RU0107 # 05 Y:1991 05 1991 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $217 $59 Not Implemented
TN0419 # 03 Y:1991 03 1991 INSTALL / REPAIR INSULATION ON STEAM LINES $2,007 $1,042 Not Implemented
TN0421 # 01 Y:1991 01 1991 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $30,358 $17,288 Implemented
TN0421 # 03 Y:1991 03 1991 CLOSE OFF UNNEEDED STEAM LINES $1,536 $0 Implemented
TN0421 # 04 Y:1991 04 1991 COVER OPEN TANKS $944 $500 Implemented
TN0421 # 05 Y:1991 05 1991 USE MINIMUM STEAM OPERATING PRESSURE $417 $0 Implemented
WI0109 # 06 Y:1991 06 1991 RECOVER WASTE HEAT FROM EQUIPMENT $716 $800 Implemented
WI0106 # 01 Y:1991 01 1991 INSULATE BARE EQUIPMENT $32,440 $10,800 Not Implemented
WI0106 # 04 Y:1991 04 1991 RECOVER WASTE HEAT FROM EQUIPMENT $1,862 $800 Not Implemented
WI0107 # 08 Y:1991 08 1991 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $3,042 $5,000 Implemented
WI0108 # 07 Y:1991 07 1991 INSULATE BARE EQUIPMENT $271 $117 Implemented
TN0420 # 10 Y:1991 10 1991 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $82 $50 Implemented
TN0420 # 05 Y:1991 05 1991 RECOVER WASTE HEAT FROM EQUIPMENT $330 $980 Implemented
AM0106 # 01 Y:1991 01 1991 UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING $6,600 $24,750 Not Implemented
AM0106 # 06 Y:1991 06 1991 USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD $80 $0 Not Implemented
AM0108 # 07 Y:1991 07 1991 INSULATE BARE EQUIPMENT $96 $426 Implemented
AM0109 # 03 Y:1991 03 1991 MODERATE COOLING TOWER OUTLET TEMPERATURE $550 $0 Implemented
AS0016 # 03 Y:1991 03 1991 INSTALL / REPAIR INSULATION ON STEAM LINES $397 $536 Implemented
AS0016 # 04 Y:1991 04 1991 REPAIR AND ELIMINATE STEAM LEAKS $2,612 $200 Implemented
AS0016 # 05 Y:1991 05 1991 INSULATE BARE EQUIPMENT $8,146 $6,624 Implemented
AS0018 # 04 Y:1991 04 1991 RECOVER WASTE HEAT FROM EQUIPMENT $392 $1,170 Not Implemented
KU0331 # 04 Y:1991 04 1991 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR $3,445 $10,200 Not Implemented
KU0331 # 07 Y:1991 07 1991 RECOVER WASTE HEAT FROM EQUIPMENT $5,925 $14,000 Not Implemented
KU0332 # 06 Y:1991 06 1991 HEAT WATER WITH EXHAUST HEAT $6,621 $8,000 Implemented
MA0201 # 01 Y:1991 01 1991 INSULATE BARE EQUIPMENT $2,084 $1,762 Not Implemented