Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,719
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0335 # 04 Y:1998 | 04 | 1998 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $310 | $0 | Implemented |
OR0334 # 01 Y:1998 | 01 | 1998 | CONDENSE OPERATION INTO ONE BUILDING | $1,080,150 | $1,000,000 | Implemented |
OR0334 # 02 Y:1998 | 02 | 1998 | INSTALL EQUIPMENT TO MOVE PRODUCT | $14,550 | $31,520 | Implemented |
OR0334 # 05 Y:1998 | 05 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,499 | $6,000 | Implemented |
OR0334 # 06 Y:1998 | 06 | 1998 | UPGRADE CONTROLS ON COMPRESSORS | $14,409 | $9,600 | Implemented |
OR0334 # 07 Y:1998 | 07 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,890 | $0 | Implemented |
OR0334 # 08 Y:1998 | 08 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $5,250 | $0 | Implemented |
OR0333 # 01 Y:1998 | 01 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $19,985 | $0 | Implemented |
OR0332 # 02 Y:1998 | 02 | 1998 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $5,644 | $0 | Implemented |
OR0332 # 05 Y:1998 | 05 | 1998 | OPTIMIZE PLANT POWER FACTOR | $0 | $54,400 | Implemented |
OR0332 # 06 Y:1998 | 06 | 1998 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,450 | $0 | Implemented |
OR0332 # 10 Y:1998 | 10 | 1998 | USE OTHER WASTE CONCENTRATION METHODS | $68,930 | $131,400 | Implemented |
OR0328 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,828 | $1,000 | Implemented |
OR0328 # 03 Y:1998 | 03 | 1998 | INSULATE BARE EQUIPMENT | $1,700 | $5,385 | Implemented |
OR0328 # 05 Y:1998 | 05 | 1998 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,386 | $0 | Implemented |
OR0326 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,653 | $1,000 | Implemented |
OR0326 # 04 Y:1998 | 04 | 1998 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,856 | $1,210 | Implemented |
OR0326 # 07 Y:1998 | 07 | 1998 | USE OTHER WASTE CONCENTRATION METHODS | $20,930 | $13,295 | Implemented |
OR0325 # 03 Y:1998 | 03 | 1998 | ADJUST BURNERS FOR EFFICIENT OPERATION | $4,674 | $0 | Implemented |
OR0324 # 06 Y:1998 | 06 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,935 | $2,000 | Implemented |
OR0324 # 07 Y:1998 | 07 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,860 | $3,700 | Implemented |
OR0324 # 08 Y:1998 | 08 | 1998 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,460 | $1,060 | Implemented |
OR0323 # 01 Y:1998 | 01 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,329 | $15,000 | Implemented |
OR0323 # 02 Y:1998 | 02 | 1998 | UPGRADE CONTROLS ON COMPRESSORS | $33,509 | $5,600 | Implemented |
OR0323 # 03 Y:1998 | 03 | 1998 | RECOVER AND REUSE WASTE MATERIAL | $16,330 | $15,000 | Implemented |