Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,719
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0697 # 03 Y:2018 | 03 | 2018 | INSULATE BARE EQUIPMENT | $25,653 | $51,599 | Implemented |
OR0697 # 05 Y:2018 | 05 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,725 | $250 | Implemented |
OR0695 # 03 Y:2017 | 03 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $12,279 | $43,386 | Implemented |
OR0689 # 01 Y:2017 | 01 | 2017 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $12,509 | $19,000 | Implemented |
OR0689 # 02 Y:2017 | 02 | 2017 | PREVENT EXCESSIVE SOLVENT USAGE (OPERATOR TRAINING) | $18,000 | $1,495 | Implemented |
OR0689 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,595 | $5,595 | Implemented |
OR0684 # 02 Y:2017 | 02 | 2017 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $17,412 | $20,340 | Implemented |
OR0684 # 04 Y:2017 | 04 | 2017 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $1,832 | $670 | Implemented |
OR0684 # 05 Y:2017 | 05 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,474 | $8,100 | Implemented |
OR0684 # 06 Y:2017 | 06 | 2017 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $229,046 | $405,000 | Implemented |
OR0684 # 07 Y:2017 | 07 | 2017 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $41,279 | $86,043 | Implemented |
OR0679 # 01 Y:2016 | 01 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $74,285 | $6,200 | Implemented |
OR0679 # 02 Y:2016 | 02 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $20,472 | $0 | Implemented |
OR0679 # 04 Y:2016 | 04 | 2016 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $31,513 | $47,575 | Implemented |
OR0679 # 05 Y:2016 | 05 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,613 | $47,385 | Implemented |
OR0678 # 02 Y:2016 | 02 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,663 | $247 | Implemented |
OR0678 # 03 Y:2016 | 03 | 2016 | INSULATE BARE EQUIPMENT | $972 | $2,626 | Implemented |
OR0677 # 01 Y:2016 | 01 | 2016 | INSULATE BARE EQUIPMENT | $7,372 | $5,408 | Implemented |
OR0677 # 05 Y:2016 | 05 | 2016 | INSULATE BARE EQUIPMENT | $2,064 | $658 | Implemented |
OR0676 # 03 Y:2016 | 03 | 2016 | REDUCE SOLUTION DRAG-OUT TO PREVENT SOLUTION LOSS | $216,607 | $80,000 | Implemented |
OR0676 # 04 Y:2016 | 04 | 2016 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $11,774 | $7,200 | Implemented |
OR0676 # 05 Y:2016 | 05 | 2016 | ADD AREA LIGHTING SWITCHES | $1,356 | $1,062 | Implemented |
OR0676 # 06 Y:2016 | 06 | 2016 | INSULATE BARE EQUIPMENT | $2,884 | $6,584 | Implemented |
OR0671 # 05 Y:2016 | 05 | 2016 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $2,295 | $1,000 | Implemented |
OR0670 # 02 Y:2016 | 02 | 2016 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $13,371 | $5,100 | Implemented |