Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,503
matching recommendationsNAICS | 332 | Fabricated Metal Product Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0509 # 09 Y:2015 | 09 | 2015 | DEVELOP A REPAIR/REPLACE POLICY | $553 | $634 | Implemented |
WM0069 # 02 Y:2015 | 02 | 2015 | REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT | $30,131 | $24,450 | Implemented |
WM0069 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19,294 | $2,400 | Implemented |
WM0069 # 06 Y:2015 | 06 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $27,723 | $0 | Implemented |
WM0069 # 09 Y:2015 | 09 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,822 | $6,100 | Implemented |
UD0927 # 02 Y:2015 | 02 | 2015 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $5,025 | $0 | Implemented |
UD0927 # 03 Y:2015 | 03 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,022 | $300 | Implemented |
MA0745 # 02 Y:2015 | 02 | 2015 | INSTALL OCCUPANCY SENSORS | $1,433 | $1,224 | Implemented |
MA0745 # 03 Y:2015 | 03 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,022 | $36,150 | Implemented |
MZ0186 # 01 Y:2015 | 01 | 2015 | INSTALL OCCUPANCY SENSORS | $5,513 | $5,100 | Implemented |
MZ0186 # 03 Y:2015 | 03 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,104 | $1,160 | Implemented |
MZ0186 # 04 Y:2015 | 04 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $83 | $0 | Implemented |
UA0140 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,787 | $1,522 | Implemented |
UA0140 # 05 Y:2015 | 05 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,564 | $1,260 | Implemented |
BD0460 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,753 | $500 | Implemented |
BD0460 # 04 Y:2015 | 04 | 2015 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $741 | $20 | Implemented |
BD0460 # 06 Y:2015 | 06 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $263 | $25 | Implemented |
BD0460 # 07 Y:2015 | 07 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $505 | $500 | Implemented |
TT0154 # 05 Y:2015 | 05 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $5,176 | $40 | Implemented |
TT0153 # 04 Y:2015 | 04 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,651 | $225 | Implemented |
TT0153 # 06 Y:2015 | 06 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,247 | $3,000 | Implemented |
TT0153 # 07 Y:2015 | 07 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,849 | $125 | Implemented |
BS0054 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29 | $45 | Implemented |
BS0054 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $597 | $4,830 | Implemented |
BS0054 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $75 | $374 | Implemented |