Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

97

matching recommendations
Reset
SIC 3089 Plastics Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TT0289 # 06 Y:2023 06 2023 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $61,137 $119,000 Implemented
TT0289 # 04 Y:2023 04 2023 RECOVER WASTE HEAT FROM EQUIPMENT $13,798 $13,000 Implemented
TT0289 # 02 Y:2023 02 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,365 $1,405 Implemented
TT0289 # 01 Y:2023 01 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,836 $40 Implemented
TT0262 # 05 Y:2021 05 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,023 $2,762 Implemented
TT0262 # 04 Y:2021 04 2021 INSULATE BARE EQUIPMENT $4,646 $3,879 Implemented
TT0232 # 02 Y:2019 02 2019 OPTIMIZE PLANT POWER FACTOR $22,260 $107,529 Implemented
TT0203 # 06 Y:2018 06 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,480 $4,250 Implemented
TT0203 # 01 Y:2018 01 2018 COMBINE UTILITY METERS $273,385 $25,000 Implemented
TT0203 # 02 Y:2018 02 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $51,897 $23,022 Implemented
TT0155 # 04 Y:2015 04 2015 INSULATE BARE EQUIPMENT $8,513 $625 Implemented
TT0155 # 01 Y:2015 01 2015 UPGRADE CONTROLS ON COMPRESSORS $35,244 $50 Implemented
TT0155 # 05 Y:2015 05 2015 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,382 $3,000 Implemented
TT0155 # 03 Y:2015 03 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $35,646 $40,000 Implemented
TT0155 # 02 Y:2015 02 2015 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $26,106 $30,000 Implemented
TT0121 # 03 Y:2013 03 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $47 $75 Implemented
TT0121 # 01 Y:2013 01 2013 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,465 $100 Implemented
TT0121 # 07 Y:2013 07 2013 UPGRADE CONTROLS ON COMPRESSORS $464 $800 Implemented
TT0121 # 06 Y:2013 06 2013 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,685 $8,460 Implemented
TT0085 # 07 Y:2012 07 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $421 $3,440 Implemented
TT0085 # 05 Y:2012 05 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,813 $8,867 Implemented
TT0085 # 06 Y:2012 06 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,203 $3,940 Implemented
TT0085 # 08 Y:2012 08 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $312 $4,158 Implemented
TT0085 # 09 Y:2012 09 2012 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $83,427 $175,342 Implemented
TT0082 # 04 Y:2011 04 2011 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $1,256 $1,480 Implemented