IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

91

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SD0229 # 03 Y:1999 03 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,665 $500 Implemented
SD0229 # 04 Y:1999 04 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,377 $120 Implemented
SD0229 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,875 $2,988 Implemented
SD0230 # 08 Y:1999 08 1999 $0 $2,410 Implemented
SD0230 # 05 Y:1999 05 1999 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $83,680 $0 Implemented
SD0230 # 01 Y:1999 01 1999 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $3,090 $4,048 Implemented
SD0230 # 07 Y:1999 07 1999 ELIMINATE PRACTICE OF MIXING WASTE STREAMS $27,200 $0 Implemented
SD0235 # 14 Y:1999 14 1999 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $4,362 $1,078 Implemented
SD0235 # 04 Y:1999 04 1999 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $18,218 $23,830 Implemented
SD0235 # 13 Y:1999 13 1999 $3,960 $0 Implemented
SD0235 # 11 Y:1999 11 1999 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $21,793 $0 Implemented
SD0234 # 04 Y:1999 04 1999 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,069 $1,425 Implemented
SD0233 # 02 Y:1999 02 1999 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,292 $360 Implemented
SD0233 # 03 Y:1999 03 1999 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $940 $584 Implemented
SD0233 # 01 Y:1999 01 1999 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $331 $725 Implemented
SD0233 # 05 Y:1999 05 1999 MAINTAIN MACHINES TO REDUCE LEAKS $6,160 $0 Implemented
SD0233 # 04 Y:1999 04 1999 RECOVER WASTE HEAT FROM EQUIPMENT $1,392 $1,394 Implemented
SD0232 # 01 Y:1999 01 1999 INSTALL SPECTRAL REFLECTORS / DELAMP $8,010 $11,160 Implemented
SD0232 # 02 Y:1999 02 1999 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $7,708 $21,250 Implemented
SD0232 # 07 Y:1999 07 1999 $1,595 $7,000 Implemented
SD0231 # 03 Y:1999 03 1999 $7,020 $0 Implemented
SD0231 # 01 Y:1999 01 1999 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,674 $10,286 Implemented
SD0224 # 01 Y:1999 01 1999 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,270 $800 Implemented
SD0224 # 02 Y:1999 02 1999 INSTALL SPECTRAL REFLECTORS / DELAMP $2,072 $2,565 Implemented
SD0224 # 06 Y:1999 06 1999 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS $8,640 $0 Implemented