IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,629

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UM0197 # 02 Y:2001 02 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,532 $825 Implemented
UM0197 # 03 Y:2001 03 2001 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,898 $1,000 Implemented
UM0197 # 06 Y:2001 06 2001 MINIMIZE WATER USAGE $44,000 $22,000 Implemented
UM0196 # 01 Y:2001 01 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,119 $4,832 Implemented
UM0196 # 02 Y:2001 02 2001 OPTIMIZE PLANT POWER FACTOR $8,645 $19,064 Implemented
UM0196 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,004 $450 Implemented
UM0196 # 04 Y:2001 04 2001 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $6,496 $2,500 Implemented
UM0196 # 06 Y:2001 06 2001 ELIMINATE SHUTDOWNS OF CONTROLS DUE TO OVERHEATING $46,825 $45,535 Implemented
UM0195 # 02 Y:2001 02 2001 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $329 $500 Implemented
UM0195 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,182 $375 Implemented
UM0193 # 02 Y:2001 02 2001 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,550 $3,000 Implemented
UM0193 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,556 $675 Implemented
UM0193 # 04 Y:2001 04 2001 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,365 $1,000 Implemented
UM0193 # 06 Y:2001 06 2001 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $341 $200 Implemented
UM0193 # 10 Y:2001 10 2001 REDESIGN PROCESS $40,150 $2,500 Implemented
UM0193 # 11 Y:2001 11 2001 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $27,400 $1,000 Implemented
UM0192 # 01 Y:2001 01 2001 OPTIMIZE PLANT POWER FACTOR $27,600 $7,600 Implemented
UM0192 # 03 Y:2001 03 2001 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,341 $800 Implemented
UM0192 # 04 Y:2001 04 2001 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $6,130 $3,850 Implemented
UM0192 # 05 Y:2001 05 2001 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $700 $700 Implemented
UM0192 # 06 Y:2001 06 2001 RECOVER AND REUSE WASTE MATERIAL $21,000 $20,000 Implemented
UM0191 # 03 Y:2001 03 2001 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $9,050 $3,150 Implemented
UM0190 # 01 Y:2001 01 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $81,576 $80,632 Implemented
UM0190 # 05 Y:2001 05 2001 OPTIMIZE PLANT POWER FACTOR $20,286 $8,250 Implemented
UM0187 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,181 $375 Implemented