Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,142
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MO0260 # 06 Y:1999 | 06 | 1999 | USE SYNTHETIC LUBRICANT | $710 | $174 | Implemented |
MO0260 # 07 Y:1999 | 07 | 1999 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $1,440 | $1,440 | Implemented |
MO0259 # 01 Y:1999 | 01 | 1999 | REPLACE BOILER | $16,318 | $2,000 | Implemented |
MO0259 # 02 Y:1999 | 02 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,876 | $566 | Implemented |
MO0259 # 03 Y:1999 | 03 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,994 | $4,410 | Implemented |
MO0259 # 05 Y:1999 | 05 | 1999 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $48 | $80 | Implemented |
MO0259 # 07 Y:1999 | 07 | 1999 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $13,260 | $1,732 | Implemented |
MO0258 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,911 | $4,897 | Implemented |
MO0258 # 02 Y:1999 | 02 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,257 | $3,392 | Implemented |
MO0258 # 05 Y:1999 | 05 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,750 | $450 | Implemented |
MO0258 # 07 Y:1999 | 07 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $60,000 | $27,500 | Implemented |
MO0257 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,831 | $0 | Implemented |
MO0257 # 02 Y:1999 | 02 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,596 | $0 | Implemented |
MO0257 # 03 Y:1999 | 03 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,342 | $0 | Implemented |
MO0257 # 07 Y:1999 | 07 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $11,004 | $0 | Implemented |
MO0256 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,574 | $10,069 | Implemented |
MO0256 # 02 Y:1999 | 02 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,533 | $3,290 | Implemented |
MO0256 # 08 Y:1999 | 08 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,520 | $3,700 | Implemented |
MO0253 # 01 Y:1999 | 01 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,142 | $5,326 | Implemented |
MO0253 # 03 Y:1999 | 03 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,044 | $40 | Implemented |
MO0253 # 04 Y:1999 | 04 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,393 | $58 | Implemented |
MO0253 # 05 Y:1999 | 05 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,322 | $0 | Implemented |
MO0253 # 07 Y:1999 | 07 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $14,000 | $3,700 | Implemented |
MO0252 # 01 Y:1999 | 01 | 1999 | INSTALL SENSORS TO DETECT DEFECTS | $101,434 | $15,624 | Implemented |
MO0252 # 02 Y:1999 | 02 | 1999 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $5,875 | $10,000 | Implemented |