IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,075

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
GT0797 # 06 Y:2005 06 2005 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $7,716 $400 Implemented
GT0797 # 07 Y:2005 07 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,447 $3,692 Implemented
IA0359 # 02 Y:2005 02 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $774 $76 Implemented
IA0359 # 03 Y:2005 03 2005 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $6,024 $790 Implemented
IA0359 # 05 Y:2005 05 2005 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $518 $30,000 Implemented
IA0359 # 06 Y:2005 06 2005 INSTALL OCCUPANCY SENSORS $299 $504 Implemented
IA0359 # 07 Y:2005 07 2005 ADJUST BURNERS FOR EFFICIENT OPERATION $1,436 $1,000 Implemented
IC0094 # 03 Y:2005 03 2005 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER $24,437 $32,056 Implemented
IC0094 # 04 Y:2005 04 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,623 $3,900 Implemented
LE0207 # 01 Y:2005 01 2005 REPLACE BOILER $109,438 $9,760 Implemented
LE0207 # 03 Y:2005 03 2005 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $21,328 $8,300 Implemented
LE0207 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,115 $1,000 Implemented
LE0207 # 06 Y:2005 06 2005 INSTALL TIMERS AND/OR THERMOSTATS $1,341 $500 Implemented
LE0207 # 07 Y:2005 07 2005 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $851 $500 Implemented
LE0206 # 02 Y:2005 02 2005 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $31,193 $5,000 Implemented
LE0206 # 03 Y:2005 03 2005 $11,880 $14,100 Implemented
LE0206 # 06 Y:2005 06 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $683 $200 Implemented
SU0204 # 04 Y:2005 04 2005 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $175 $0 Implemented
SU0204 # 07 Y:2005 07 2005 USE SYNTHETIC LUBRICANT $3,145 $2,000 Implemented
NC0309 # 01 Y:2005 01 2005 $89,630 $5,000 Implemented
NC0309 # 02 Y:2005 02 2005 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL $9,148 $21,000 Implemented
NC0309 # 04 Y:2005 04 2005 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,268 $6,500 Implemented
NC0309 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,767 $100 Implemented
OK0702 # 05 Y:2005 05 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $234 $530 Implemented
AM0481 # 02 Y:2005 02 2005 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,990 $600 Implemented