Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
845
matching recommendationsSIC | 335 | Nonferrous Rolling And Drawing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
CO0473 # 03 Y:2000 | 03 | 2000 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $6,360 | $10,000 | Implemented |
CO0473 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,980 | $1,000 | Implemented |
CO0473 # 05 Y:2000 | 05 | 2000 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,180 | $6,780 | Implemented |
CO0473 # 06 Y:2000 | 06 | 2000 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $1,260 | $500 | Implemented |
CO0473 # 07 Y:2000 | 07 | 2000 | USE IN-PROCESS RECYCLING WHENEVER POSSIBLE | $107,610 | $75,000 | Implemented |
CO0473 # 08 Y:2000 | 08 | 2000 | USE IN-PROCESS RECYCLING WHENEVER POSSIBLE | $39,460 | $10,000 | Implemented |
ND0361 # 01 Y:2000 | 01 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $695 | $100 | Implemented |
ND0361 # 05 Y:2000 | 05 | 2000 | DEVELOP A REPAIR/REPLACE POLICY | $4,112 | $41,893 | Implemented |
ND0361 # 06 Y:2000 | 06 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,329 | $400 | Implemented |
SD0256 # 01 Y:2000 | 01 | 2000 | INSTALL SKYLIGHTS | $18,038 | $27,000 | Implemented |
SD0256 # 02 Y:2000 | 02 | 2000 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,703 | $7,230 | Implemented |
SD0256 # 05 Y:2000 | 05 | 2000 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $290,738 | $0 | Implemented |
UM0163 # 02 Y:2000 | 02 | 2000 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $1,248 | $0 | Implemented |
UM0163 # 03 Y:2000 | 03 | 2000 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $2,496 | $500 | Implemented |
UM0163 # 04 Y:2000 | 04 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,147 | $300 | Implemented |
UM0163 # 09 Y:2000 | 09 | 2000 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $56,997 | $90,000 | Implemented |
GT0681 # 05 Y:1999 | 05 | 1999 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $12,917 | $4,800 | Implemented |
UL0237 # 02 Y:1999 | 02 | 1999 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $11,512 | $0 | Implemented |
UF0233 # 02 Y:1999 | 02 | 1999 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $1,008 | $750 | Implemented |
UF0233 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,649 | $320 | Implemented |
UF0233 # 05 Y:1999 | 05 | 1999 | USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS | $10,287 | $14,925 | Implemented |
UF0233 # 06 Y:1999 | 06 | 1999 | $33,600 | $0 | Implemented | |
GT0668 # 01 Y:1999 | 01 | 1999 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $3,706 | $0 | Implemented |
GT0668 # 04 Y:1999 | 04 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $678 | $1,000 | Implemented |
GT0668 # 05 Y:1999 | 05 | 1999 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,662 | $345 | Implemented |